Biggest changeThe sale and transfer of Broken Bow II, including the related debt, was completed in January 2025. 30 CON EDISON ANNUAL REPORT 2024 The following table contains the Companies’ capital requirements current estimate of amounts for 2029 through 2025: Estimate (Millions of Dollars) 2029 2028 2027 2026 2025 CECONY (a)(b) Electric $5,789 $6,402 $6,277 $6,033 $3,380 Gas 1,151 1,221 1,253 1,289 1,113 Steam 153 140 140 108 108 Sub-total 7,093 7,763 7,670 7,430 4,601 O&R (b) Electric 456 430 381 416 358 Gas 116 117 110 127 120 Sub-total 572 547 491 543 478 Con Edison Transmission 113 113 107 94 43 Total capital expenditures 7,778 8,423 8,268 8,067 5,122 Retirement of long-term securities Con Edison – parent company — — — — — CECONY — 800 700 250 — O&R 44 — 80 — — Total retirement of long-term securities 44 800 780 250 — Total capital requirements $7,822 $9,223 $9,048 $8,317 $5,122 (a) CECONY’s capital expenditures for environmental protection facilities and related studies are estimated to be $605 million in 2025.
Biggest changeCON EDISON ANNUAL REPORT 2025 29 The following table contains the Companies’ capital requirements current estimate of amounts for 2026 through 2030: Estimate (Millions of Dollars) 2030 2029 2028 2027 2026 CECONY (a)(b) Electric $6,293 $6,228 $5,019 $4,852 $4,766 Gas 1,451 1,436 1,066 1,057 1,093 Steam 209 223 201 193 127 Sub-total 7,953 7,887 6,286 6,102 5,986 O&R (b) Electric 479 494 502 380 415 Gas 139 143 151 110 132 Sub-total 618 637 653 490 547 Con Edison Transmission 17 75 213 167 62 Total capital expenditures 8,588 8,599 7,152 6,759 6,595 Retirement of long-term securities CECONY 600 — 800 700 250 O&R 35 44 — 80 — Total retirement of long-term securities 635 44 800 780 250 Total capital requirements $9,223 $8,643 $7,952 $7,539 $6,845 (a) CECONY’s capital expenditures for environmental protection facilities and related studies are estimated to be $637 million in 2026.
For additional segment information, see Note P to the financial statements in Item 8.
For additional segment information, see Note P to the financial statements in Item 8.
In general, the Utilities recover their costs of purchasing power for full service customers, including the cost of hedging purchase prices, pursuant to rate provisions approved by the state public utility regulatory authority having jurisdiction.
In general, the Utilities recover their costs of purchasing power for full service customers, including the cost of hedging purchase prices, pursuant to rate provisions approved by the state public utility regulatory authority having jurisdiction.
The company’s estimate of its liability for each site was determined pursuant to consent decrees, settlement agreements or otherwise and in light of the financial condition of other PRPs. The company’s actual liability could differ substantially from amounts estimated.
The company’s estimate of its liability for each site was determined pursuant to consent decrees, settlement agreements or otherwise and in light of the financial condition of other PRPs. The company’s actual liability could differ substantially from amounts estimated.
The NYSDEC issued regulations in 2019 that limit nitrous oxides (NOx) emissions during the ozone season from May through September and affect older peaking units that are generally located downstate and needed during periods of high electric demand or for local reliability purposes. See “CECONY – Electric Operations – Electric Supply,” above.
The NYSDEC issued regulations in 2019 that limit emissions of nitrous oxides (NOx) during the ozone season from May through September and affect older peaking units that are generally located downstate and needed during periods of high electric demand or for local reliability purposes. See “CECONY – Electric Operations – Electric Supply,” above.
Environmental Matters Clean Energy Future New York State’s Climate Leadership and Community Protection Act In 2019, New York State enacted the Climate Leadership and Community Protection Act (CLCPA) that established a goal of 70 percent of the electricity procured by load serving entities regulated by the NYSPSC to be produced by renewable energy systems by 2030 and requires the statewide electrical demand system to have zero emissions by 2040.
Environmental Matters Clean Energy Future New York State’s Clean Energy Goals In 2019, New York State enacted the Climate Leadership and Community Protection Act (CLCPA) that established a goal of 70 percent of the electricity procured by load serving entities regulated by the NYSPSC to be produced by renewable energy systems by 2030 and requires the statewide electrical demand system to have zero emissions by 2040.
Gas Supply CECONY and O&R have combined their gas requirements, and contracts to meet those requirements, into a single portfolio. The combined portfolio is administered by, and related management services are provided by, CECONY (for itself and as agent for O&R) and costs are allocated between the Utilities in accordance with provisions approved by the NYSPSC.
Gas Supply CECONY and O&R have combined their gas requirements, and contracts to meet those requirements, into a single portfolio. The combined portfolio is administered by, and related management services are provided by, CECONY (for itself and as an agent for O&R) and costs are allocated between the Utilities in accordance with provisions approved by the NYSPSC.
Distribution System and Distributed Resources The NYSPSC is directing development by New York electric utilities of a distributed system platform to manage and coordinate distributed energy resources in their service areas under NYSPSC regulation and to provide customers, together with third parties, with data and tools to better manage their energy use.
Distribution System and Distributed Energy Resources The NYSPSC is directing development by New York electric utilities of a distributed system platform to manage and coordinate distributed energy resources (DER) in their service areas under NYSPSC regulation and to provide customers, together with third parties, with data and tools to better manage their energy use.
Liability for Service Interruptions The tariff provisions under which CECONY provides electric, gas and steam service, and O&R provides electric and gas service, limit each company’s liability to pay for damages resulting from service interruptions to circumstances resulting from its gross negligence or willful misconduct.
Liability for Service Interruptions The tariff provisions under which CECONY provides electric, gas and steam service, and O&R provides electric and gas service, limit each company’s liability to pay for damages resulting from service interruptions due to circumstances resulting from its gross negligence or willful misconduct.
(a subsidiary of Fortis Inc.) – or one of two state authorities – New York Power Authority (NYPA) or Long Island Power Authority. 16 CON EDISON ANNUAL REPORT 2024 Rate Plans Investor-owned utilities in the United States provide delivery service to customers according to the terms of tariffs approved by the appropriate state utility regulator.
(a subsidiary of Fortis Inc.) – or one of two state authorities – New York Power Authority (NYPA) or Long Island Power Authority. 16 CON EDISON ANNUAL REPORT 2025 Rate Plans Investor-owned utilities in the United States provide delivery service to customers according to the terms of tariffs approved by the appropriate state utility regulator.
Since NYISO-invoked demand reduction programs can only be called upon under specific circumstances, Design Weather Conditions do not include these programs' potential impact. However, the O&R forecasted hourly peak demand at design conditions does include the impact of certain demand reduction programs. The company estimates that, under Design Weather Conditions, the 2025 service area peak demand will be 1,600 MW.
Since NYISO-invoked demand reduction programs can only be called upon under specific circumstances, design weather conditions do not include these programs' potential impact. However, the O&R forecasted hourly peak demand at design conditions does include the impact of certain demand reduction programs. The company estimates that, under design weather conditions, the 2026 service area peak demand will be 1,600 MW.
CON EDISON ANNUAL REPORT 2024 15 O&R Electric O&R and its utility subsidiary, Rockland Electric Company (RECO) (together referred to herein as O&R) provide electric service to approximately 0.3 million customers in southeastern New York and northern New Jersey, an approximately 1,300 square mile service area. Gas O&R delivers gas to over 0.1 million customers in southeastern New York.
CON EDISON ANNUAL REPORT 2025 15 O&R Electric O&R and its utility subsidiary, Rockland Electric Company (RECO) (together referred to herein as O&R) provide electric service to approximately 0.3 million customers in southeastern New York and northern New Jersey, an approximately 1,300 square mile service area. Gas O&R delivers gas to over 0.1 million customers in southeastern New York.
See “Con Edison Transmission,” below. 18 CON EDISON ANNUAL REPORT 2024 New York Independent System Operator (NYISO) The NYISO is a not-for-profit organization that controls and directs the operation of most of the electric transmission facilities in New York State, including those of the Utilities, as an integrated system.
See “Con Edison Transmission,” below. 18 CON EDISON ANNUAL REPORT 2025 New York Independent System Operator (NYISO) The NYISO is a not-for-profit organization that controls and directs the operation of most of the electric transmission facilities in New York State, including those of the Utilities, as an integrated system.
The company expects that these resources will again be adequate to meet the requirements of its customers in 2025. O&R does not own any electric generating capacity. The company plans to meet its continuing obligation to supply electricity to its customers through a combination of electricity purchased under contracts or purchased through the wholesale electricity market.
The company expects that these resources will again be adequate to meet the requirements of its customers in 2026. O&R does not own any electric generating capacity. The company plans to meet its continuing obligation to supply electricity to its customers through a combination of electricity purchased under contracts or purchased through the wholesale electricity market.
The order also provides CECONY and O&R with authorization to offer incentives to encourage electric vehicle charging to occur overnight and during off-peak times totaling approximately $71.8 million and $8.2 million, respectively, through 2025, that would be recovered through the respective company’s revenue reconciliation mechanisms.
The order also provided CECONY and O&R with authorization to offer incentives to encourage electric vehicle charging to occur overnight and during off-peak times totaling approximately $71.8 million and $8.2 million, respectively, through 2025, that would be recovered through the respective company’s revenue reconciliation mechanisms.
As required by the law, the New York State Department of Environmental Conservation (NYSDEC) adopted regulations establishing statewide GHG emissions limits that are 60 percent of 1990 emissions levels by 2030 and 15 percent of 1990 emissions by 2050. The Utilities are unable to predict the impact on them of the implementation of this law.
As required by the law, the New York State Department of Environmental Conservation (NYSDEC) adopted regulations establishing statewide GHG emissions limits that are 60 percent of 1990 emissions levels by 2030 and 15 percent of 1990 emissions by 2050. The Utilities are unable to predict the impact that the implementation of this law will have on them.
The five-year forecast in peak demand is used by the company for electric supply and capital expenditures planning purposes. Electric Supply The electricity O&R sold to its full-service customers in 2024 was purchased under firm power contracts or through the wholesale electricity market.
The five-year forecast in peak demand is used by the company for electric supply and capital expenditures planning purposes. Electric Supply The electricity O&R sold to its full-service customers in 2025 was purchased under firm power contracts or through the wholesale electricity market.
The five-year forecast in peak demand is used by the company for electric supply and capital expenditures planning purposes. Electric Supply Most of the electricity sold by CECONY to its full-service customers in 2024 was purchased through the wholesale electricity market administered by the NYISO.
The five-year forecast in peak demand is used by the company for electric supply and capital expenditures planning purposes. Electric Supply Most of the electricity sold by CECONY to its full-service customers in 2025 was purchased through the wholesale electricity market administered by the NYISO.
At “Design Weather Conditions,” electric peak demand in O&R’s service area would have been approximately 1,533 MW. Design Weather Conditions for the electric system is a standard to which the actual hourly peak demand is adjusted for evaluation and planning purposes.
At “design weather conditions,” electric peak demand in O&R’s service area would have been approximately 1,526 MW. Design weather conditions for the electric system is a standard to which the actual hourly peak demand is adjusted for evaluation and planning purposes.
In December 2024, CECONY and O&R each submitted updated emergency response plans for 2025. Generic Proceedings The NYSPSC from time to time conducts “generic” proceedings to consider issues relating to all electric and gas utilities operating in New York State.
In December 2025, CECONY and O&R each submitted updated emergency response plans for 2026. Generic Proceedings The NYSPSC from time to time conducts “generic” proceedings to consider issues relating to all electric and gas utilities operating in New York State.
At “Design Weather Conditions,” electric peak demand in CECONY’s service area would have been approximately 12,540 MW. Design Weather Conditions for the electric system is a standard to which the actual hourly peak demand is adjusted for evaluation and planning purposes.
At “design weather conditions,” electric peak demand in CECONY’s service area would have been approximately 12,600 MW. Design weather conditions for the electric system is a standard to which the actual hourly peak demand is adjusted for evaluation and planning purposes.
Gas Con Edison Transmission owns a 71.2 percent interest in Honeoye, a company that operates a gas storage facility in upstate New York and in which CECONY owns the remaining interest. Con Edison Transmission and CECONY are considering strategic alternatives with respect to their investments in Honeoye.
Gas Con Edison Transmission owns a 71.2 percent inter est in Honeoye, a company that operates a gas storage facility in upstate New York and in which CECONY owns the remaining interest. Con Edison Transmission and CECONY are considering strategic alternatives with respect to their investments in Honeoye.
The collective bargaining agreement covering most of the CECONY employees expires in June 2028. Agreements covering other CECONY employees and O&R employees expire in June 2025 and May 2026, respectively. Con Edison measures the voluntary attrition rate of its employees in assessing the company’s overall human capital.
The collective bargaining agreement covering most of the CECONY employees expires in June 2028 . Agreements covering other CECONY employees and O&R employees expire in June 2029 and May 2026, respectively. Con Edison measures the voluntary attrition rate of its employees in assessing the company’s overall human capital.
The plaintiff asserts claims pursuant to the federal Comprehensive Environmental Response, Compensation and Liability Act of 1980 and the New York Navigation Law for cleanup costs incurred, and to be incurred, by the plaintiff at the site. The plaintiff estimates the total cleanup costs at the site to be over $1,000 million.
The plaintiff asserts claims pursuant to the federal Comprehensive Environmental Response, Compensation and Liability Act of 1980 and the New York Navigation Law for cleanup costs incurred, and to be incurred, by the plaintiff at the site. The plaintiff estimated the total cleanup costs at the site to be over $1,000 million.
(c) Propel NY Energy, a project that is under development jointly with the NYPA, is a 90-mile electric transmission project that is expected to increase high voltage transmission connections between Long Island and the rest of New York State.
(d) Propel NY Energy, a project that is under development jointly with the NYPA, is a 90-mile electric transmission project that is expected to increase high voltage transmission connections between Long Island and the rest of New York State.
NYSERDA has issued competitive solicitations for offshore wind energy resulting in two projects that are in development, Sunrise Wind (924 MW), a project that began construction in June 2024 and is expected to enter commercial operation in 2026 and Empire Wind 1 (810 MW), a project that is expected to enter commercial operation in 2027 and connect to the New York City electrical grid at CECONY’s Gowanus substation.
NYSERDA issued competitive solicitations for offshore wind energy resulting in two projects that are in development, Sunrise Wind (924 MW), a project that began construction in June 2024 and that is expected to enter commercial operation in 2026 and Empire Win d 1 (810 MW), a project that is expected to enter commercial operation in 2027 and connect to the New York City electrical grid at CECONY’s Gowanus substation.
The EPA estimated the cost of this work would be $369 million (although actual costs may be significantly higher) and has indicated the work would take several years to complete. In October 2024, a PRP filed a lawsuit against the other PRPs, including CECONY, with respect to the Gowanus Canal Superfund Site.
The EPA estimated the cost of this work would be $369 million (although actual costs may be significantly higher) and has indicated the work would take several years to complete. In October 2024, a PRP filed a lawsuit against the other PRPs, including CECONY, with respect to the Gowanus Canal Sup erfund Site.
Further, the company maintains a career development and succes sion planning program that is committed to helping employees grow their careers, talents, skills and abilities. In addition to their daily job functions, employees of the Utilities are assigned to and trained for a position for emergency response that is mobilized in the event of a weather event or emergency.
Further, the company maintains a career development and succes sion planning program that is committed to helping employees grow their careers, talents, skills and abilities. In addition to their daily job functions, employees of the Utilities are assigned to and trained for a position for emergency response that can be mobilized to support a weather event or emergency.
CON EDISON ANNUAL REPORT 2024 41 Site Location Start Court or Agency % of Total Liability Cortese Landfill Narrowsburg, NY 1987 EPA 6.0% Curcio Scrap Metal Saddle Brook, NJ 1987 EPA 100.0% Metal Bank of America Philadelphia, PA 1987 EPA 1.0% Global Landfill Old Bridge, NJ 1988 EPA 0.4% Borne Chemical Elizabeth, NJ 1997 NJDEP 0.7% Pure Earth Vineland, NJ 2018 EPA to be determined Berry's Creek Site (formerly referred to as Scientific Chemical Processing) Carlstadt, NJ 2023 EPA to be determined Other Environmental Matters In December 2024, New York State enacted the Climate Change Superfund Act (Act), which requires "responsible parties" to pay $75 billion over twenty-five years into a fund based on GHG emissions to finance infrastructure projects needed to address the impacts from climate change.
Site Location Start Court or Agency % of Total Liability Cortese Landfill Narrowsburg, NY 1987 EPA 6.0% Curcio Scrap Metal Saddle Brook, NJ 1987 EPA 100.0% Metal Bank of America Philadelphia, PA 1987 EPA 1.0% Global Landfill Old Bridge, NJ 1988 EPA 0.4% Borne Chemical Elizabeth, NJ 1997 NJDEP 0.7% Pure Earth Vineland, NJ 2018 EPA to be determined Berry's Creek Site (formerly referred to as Scientific Chemical Processing) Carlstadt, NJ 2023 EPA to be determined Other Environmental Matters In December 2024, New York State enacted the Climate Change Superfund Act (Act), which requires, among other things, "responsible parties" to pay $75 billion over twenty-five years into a fund based on GHG emissions to finance infrastructure projects needed to address the impacts from climate change.
(e) Included in these amounts is the cost of minimum quantities of natural gas supply, transportation and storage that the Utilities are obligated to purchase at both fixed and variable prices.
(d) Included in these amounts is the cost of minimum quantities of natural gas supply, transportation and storage that the Utilities are obligated to purchase at both fixed and variable prices.
These requirements apply both to regulated utilities such as CECONY and O&R for the customers they supply under regulated tariffs and to other load serving entities that supply customers on market terms. See “CECONY – Electric Operations – Electric Supply” and “O&R – Electric Operations – Electric Supply,” below.
These requirements apply both to regulated utilities such as CECONY and O&R for the customers they supply under regulated tariffs and to other load serving entities that supply customers on market terms. See “CECONY – Electric Operations – Electric Supply,” "CECONY – Electric Operations – Electric Reliability Needs" and “O&R – Electric Operations – Electric Supply,” below.
If, after evidentiary hearings or other investigatory proceedings, the NYSPSC finds that the utility failed to reasonably implement its plan during an event, the NYSPSC may impose penalties or deny recovery of any part of the service restoration costs caused by such failure. In April 2024, the NYSPSC approved CECONY’s and O&R's emergency response plans.
If, after evidentiary hearings or other investigatory proceedings, the NYSPSC finds that the utility failed to reasonably implement its plan during an event, the NYSPSC may impose penalties or deny recovery of any part of the service restoration costs caused by such failure. In March 2025, the NYSPSC approved CECONY’s and O&R's emergency response plans.
The NYSPSC recommended adoption of specific cybersecurity regulations to enhance and codify standards and practices in these areas, which will be developed and implemented in a future proceeding. O&R’s subsidiary, RECO, is subject to cyber regulation by the NJBPU.
The NYSPSC recommended adoption of specific cybersecurity regulations to enhance and codify standards and practices in these areas, which will be developed and implemented pursuant to a separate proceeding. O&R’s subsidiary, RECO, is subject to cyber regulation by the NJBPU.
The Companies are unable to predict changes in regulations, regulatory guidance, legal interpretations, policy positions and implementation actions that may result from the Presidential Actions.
The Companies are unable to predict changes in regulations, regulatory guidance, legal interpretations, policy positions and implementation actions that may result from the Federal Actions.
Long-term Purchase Obligations, which co mprises $3,126 million of "Other Purchase Obligations," were derived from the Utilities' purchasing system by using a method that identifies the remaining purchase obligations. The Utilities believe that unreasonable effort and expense would be involved to enable them to report their “Other Purchase Obligations” in a different manner.
Long-term Purchase Obligations, which co mprises $3,116 million of "Other Pur chase Obligations," were derived from the Utilities' purchasing system by using a method that identifies the remaining purchase obligations. The Utilities believe that unreasonable effort and expense would be involved to enable them to report their “Other Purchase Obligations” in a different manner.
As of January 2025, the company forecasts an average annual decrease in steam hourly peak demand in its service area at Design Weather Conditions over the next five years to be approximately 0.4 percent. The five-year forecast in peak demand is used by the company for steam supply and capital expenditures planning purposes.
As of January 2026, the company forecasts an average annual decrease in steam hourly peak demand in its service area at design weather conditions over the next five years to be approximately 0.9 percent. The five-year forecast in peak demand is used by the company for steam supply and capital expenditures planning purposes.
As of January 2025, the company forecasts an average annual increase of the gas peak day demand for firm gas customers over the next five years at design conditions of approximately 0.1 percent in its service area. The five-year forecast in peak demand is used by the company for gas supply and capital expenditures planning purposes.
As of January 2026, the company forecasts an average annual increase of the gas peak day demand for firm gas customers over the next five years at design conditions of approximately 0.2 percent in its service area. The five-year forecast in peak demand is used by the company for gas supply and capital expenditures planning purposes.
Natural gas is delivered by pipeline to O&R at various points in or near its service territory and is distributed to customers by the company through an estimated 1,900 miles of mains and 107,745 service lines. Gas Sales and Deliveries O&R delivers gas to its full-service customers who purchase gas from the company.
Natural gas is delivered by pipeline to O&R at various points in or near its service territory and is distributed to customers by the company through an estimated 1,902 miles of mains and 107,866 service lines. Gas Sales and Deliveries O&R delivers gas to its full-service customers who purchase gas from the company.
Con Edison, as part of a coalition of public and private utilities, intervened in this litigation, arguing that the EPA had the authority to set the BSER, but the coalition took no position as to whether CCS was achievable in the timeframe set forth in the Section 111 Rule. In December 2024, the D.C.
Con Edison, as part of a coalition of public and private utilities, intervened in this litigation, arguing that the EPA had the authority to set the BSER, but the coalition took no position as to whether CCS was achievable in the timeframe set forth in the Section 111 Rule. In February 2025, the D.C.
Environmental Sustainability Con Edison’s sustainability strategy, as it relates to the environment, provides that the company seeks, among other things, to reduce direct and indirect GHG emissions; enhance the efficiency of its water use; reduce its impact to natural ecosystems; focus on reducing, reusing and recycling to lower materials consumption and disposal; and design its work in consideration of climate projections .
Environmental Sustainability CON EDISON ANNUAL REPORT 2025 37 Con Edison’s sustainability strategy, as it relates to the environment, provides that the company seeks, among other things, to reduce direct and indirect GHG emissions; enhance the efficiency of its water use; reduce its impact to natural ecosystems; focus on reducing, reusing and recycling to lower materials consumption and disposal; and design its work in consideration of climate projections .
Any such costs incurred by utilities are not recoverable from customers. Utilities may petition the NYSPSC to request a waiver of the requirement that it compensate customers after widespread prolonged outages.
Any su ch costs incurred by utilities are not recoverable from customers. Utilities may petition the NYSPSC to request a waiver of the requirement that it compensate customers after widespread prolonged outages.
“Design Weather Conditions” for the gas system is a standard to which the actual peak demand is adjusted for evaluation and planning purposes. The company estimates that, under Design Weather Conditions, the 2025/2026 service area peak day demand for firm gas customers will be 1,650 MDt.
“Design weather conditions” for the gas system is a standard to which the actual peak demand is adjusted for evaluation and planning purposes. The company estimates that, under design weather conditions, the 2026/2027 service area peak day demand for firm gas customers will be 1,648 MDt.
“Design Weather Conditions” for the steam system is a standard to which the actual hourly peak demand is adjusted for evaluation and planning purposes. The company’s estimate for the winter of 2025/2026 hourly peak demand of its steam customers is about 7.6 MMlb per hour under Design Weather Conditions.
“Design weather conditions” for the steam system is a standard to which the actual hourly peak demand is adjusted for evaluation and planning purposes. The company’s estimate for the winter of 2026/2027 hourly peak demand of its steam customers is about 7.3 MMlb per hour under design weather conditions.
“Design Weather Conditions” for the gas system is a standard to which the actual peak demand is adjusted for evaluation and planning purposes. The company estimates that, under Design Weather Conditions, the 2025/2026 service area peak day demand for firm sales customers will be 235 MDt.
“Design weather conditions” for the gas system is a standard to which the actual peak demand is adjusted for evaluation and planning purposes. The company estimates that, under design weather conditions, the 2026/2027 service area peak day demand for firm sales customers will be 247 MDt.
Gas Peak Demand The gas actual peak day demand for firm sales customers in O&R’s service area occurs during the winter heating season and during the winter of 2024/2025 (through January 31, 2025) occurred on January 21, 2025 when the firm sales customers' demand reached approximately 188 MDt.
Gas Peak Demand The gas actual peak day demand for firm sales customers in O&R’s service area occurs during the winter heating season and during the winter of 2025/2026 (through January 31, 2026) occurred on January 24, 2026 when the firm sales customers' demand reached approximately 188 MDt.
The NJBPU authorized RECO to recover these costs, including a full rate of return, in rates from customers. 36 CON EDISON ANNUAL REPORT 2024 In November 2023, the NYSPSC issued an order that provides CECONY and O&R with up to $432 million and $18 million through 2026, respectively, for the implementation of commercial managed charging programs and demand charge rebates, participant incentives and administration costs.
The NJBPU authorized RECO to recover these costs, including a full rate of return, in rates from customers. In November 2023, the NYSPSC issued an order that provides CECONY and O&R with up to $432 million and $18 million through 2026, respectively, for the implementation of commercial managed charging programs and demand charge rebates, participant incentives and administration costs.
Under the company's retail choice program, O&R also delivers electricity to its customers who purchase electricity from load serving entities. 26 CON EDISON ANNUAL REPORT 2024 The company charges all customers in its service area for the delivery of electricity.
Under the company's retail choice program, O&R also delivers electricity to its customers who purchase electricity from load serving entities. CON EDISON ANNUAL REPORT 2025 25 The company charges all customers in its service area for the delivery of electricity.
The company estimates that its undiscounted potential liability for the completion of the site investigation and cleanup of the known contamination on MGP sites (other than the Astoria site, which is discussed below) could range from $622 million to $2,432 million.
The company estimates that its undiscounted potential liability for the completion of the site investigation and cleanup of the known contamination on MGP sites (other than the Astoria site, which is discussed below) could range from $645 million to $2,550 million.
Under Clean Air Act New Source Review (NSR) regulations, an owner of a major facility, including CECONY’s steam and steam-electric generating facilities and certain other CECONY facilities, is required to obtain a permit before making certain modifications to the facility, other than routine maintenance, repair, or replacement, that cause the increase of emissions of pollutants from the facility above specified thresholds.
CON EDISON ANNUAL REPORT 2025 41 Under Clean Air Act New Source Review (NSR) regulations, an owner of a major facility, including CECONY’s steam and steam-electric generating facilities and certain other CECONY facilities, is required to obtain a permit before making certain modifications to the facility, other than routine maintenance, repair, or replacement, that cause the increase of emissions of pollutants from the facility above specified thresholds.
The NYSPSC authorized CECONY and O&R to recover these costs, including a full rate of return, through surcharge mechanisms and subsequently in rates from customers.
The NYSPSC authorized CECONY and O&R to recover these costs, including a full rate of return, through surcharge mecha nisms and subsequently in rates from customers.
Meeting the goals of the CLCPA will require capital expenditures above historic norms. While the details of CECONY’s investments will continue to be addressed in its rate cases or other filings, subject to the approval of the NYSPSC, CECONY projects that $72 billion of capital expenditures will be needed between 2025 and 2034 to implement its strategy.
Implementing this strategy will require capital expenditures above historic norms. While the details of CECONY’s investments will continue to be addressed in its rate cases or other filings, subject to the approval of the NYSPSC, CECONY projects that $72 billion of capital expenditures will be needed between 2025 and 2034 to implement its strategy.
Offshore Wind In an effort to meet the CLCPA’s offshore wind goals, load serving entities, such as CECONY and O&R, will be required to purchase offshore wind renewable energy credits beginning in 2026 when NYSERDA's offshore wind projects are expected to begin operation.
Offshore Wind In an effort to meet the CLCPA’s offshore wind goals, load serving entities, such as CECONY and O&R, will be required to purchase offshore wind renewable energy credits when NYSERDA's offshore wind projects begin operation.
O&R generally recovers, on a current basis, the cost of the electricity that it buys and then sells to its full-service customers. It does not make any margin or profit on the electricity it sells. O&R’s New York electric revenues (which accounted for 74.63 percent of O&R’s electric revenues in 2024) are subject to a revenue decoupling mechanis m.
O&R generally recovers, on a current basis, the cost of the electricity that it buys and then sells to its full-service customers. It does not make any margin or profit on the electricity it sells. O&R’s New York electric revenues (which accounted for 76.66 percent of O&R’s electric revenues in 2025) are subject to a revenue decoupling mechanis m.
For additional information about the segments, see Note P to the financial statements in Item 8. Electric Operations Electric Facilities CECONY’s capitalized costs for utility plant, net of accumulated depreciation, for distribution facilities were $23,770 million and $23,238 million at December 31, 2024 and 2023, respectively.
For additional information about the segments, see Note P to the financial statements in Item 8. Electric Operations Electric Facilities CECONY’s capitalized costs for utility plant, net of accumulated depreciation, for distribution facilities were $25,214 million and $23,770 million at December 31, 2025 and 2024, respectively.
The Companies’ commitments to make payments in addition to these contractual commitments include their other liabilities reflected on their balance sheets, any funding obligations for their pension and other postretirement benefit plans, financial hedging activities, their collective bargaining agreements and Con Edison’s guarantee of certain obligations.
CON EDISON ANNUAL REPORT 2025 31 The Companies’ commitments to make payments in addition to these contractual commitments include their other liabilities reflected on their balance sheets, any funding obligations for their pension and other postretirement benefit plans, financial hedging activities, their collective bargaining agreements and Con Edison’s guarantee of certain obligations.
CECONY’s current electric and gas rate plans allow it to recover the costs of heat pumps for building electrification and energy efficiency expenditures, including a full rate of return, in rates from customers. See Note B to the financial statements in Item 8.
CECONY’s 2023-2025 electric and gas rate plans allowed it to recover the costs of heat pumps for building electrification and energy efficiency expenditures, including a full rate of return, in rates from customers. See Note B to the financial statements in Item 8.
While the Good Neighbor Rule is stayed, the EPA is allocating allowances based on the 2021 Transport Rule, with certain modifications. The revised Transport Rule reduced the number of allowances allocated to CECONY and required the company to purchase allowances to offset the decreased allocation. CECONY expects to comply with the Transport Rule in 2024 and 2025.
While the Good Neighbor Rule is stayed, the EPA is allocating allowances base d on the 2021 Transport Rule, with certain modifications. The revised Transport Rule reduced the number of allowances allocated to CECONY and required the company to purchase allowances to offset the decreased allocation. CECONY expects to comply with the Transport Rule in 2025 and 2026.
On December 31, 2024, the steam system was capable of delivering approximately 11.5 MMlb of steam per hour, and CECONY estimates that the system will maintain the same capability throughout the 2025/2026 winter.
On December 31, 2025, the steam system was capable of delivering approximately 11.2 MMlb of steam per hour, and CECONY estimates that the system will maintain the same capability throughout the 2026/2027 winter.
For a further discussion of claims and possible claims against O&R under Superfund, see Note G to the financial statements in Item 8. Manufactured Gas Sites O&R and its predecessors formerly owned and operated manufactured gas plants at seven sites (O&R MGP Sites) in Orange County and Rockland County, New York.
For a further discussion of claims and possible claims against O&R under Superfund, see Note G to the financial statements in Item 8. Manufactured Gas Sites 40 CON EDISON ANNUAL REPORT 2025 O&R and its predecessors formerly owned and operated manufactured gas plants at seven sites (O&R MGP Sites) in Orange County and Rockland County, New York.
Steam Operations Steam Facilities CECONY’s capitalized costs for utility plant, net of accumulated depreciation, for steam facilities, including steam's portion of the steam-electric generation facilities, were $2,006 million and $1,990 million at December 31, 2024 and 2023, respectively. See "CECONY – Electric Operations – Electric Facilities," above.
Steam Operations Steam Facilities CECONY’s capitalized costs for utility plant, net of accumulated depreciation, for steam facilities, including steam's portion of the steam-electric generation facilities, were $2,009 million and $2,006 million at December 31, 2025 and 2024, respectively. See "CECONY – Electric Operations – Electric Facilities," above.
Con Edison’s estimated Scope 1 emissions of GHG during the past five years were: 38 CON EDISON ANNUAL REPORT 2024 (Metric tons, in millions (a)) 2024 2023 2022 2021 2020 CO2 equivalent emissions 2.7 2.7 2.9 2.8 2.7 (a) Estimated emissions for 2024 are based on preliminary data and are subject to third-party verification.
Con Edison’s estimated Scope 1 emissions of GHG during the past five years were: (Metric tons, in millions (a), (b)) 2025 2024 2023 2022 2021 CO2 equivalent emissions 2.7 2.7 2.7 2.9 2.8 (a) Estimated emissions for 2025 are based on preliminary data and are subject to third-party verification.
O&R’s electric sales and deliveries for the last five years were: Year Ended December 31, 2024 2023 2022 2021 2020 Electric Energy Delivered (millions of kWh) Total deliveries to O&R full service customers 3,212 2,988 2,973 2,702 2,712 Delivery service for retail choice customers 2,522 2,397 2,580 2,839 2,622 Total Deliveries in Franchise Area 5,734 5,385 5,553 5,541 5,334 Electric Energy Delivered ($ in millions) Total deliveries to O&R full service customers $653 $578 $576 $453 $442 Delivery service for retail choice customers 198 172 198 223 186 Other operating revenues 1 9 (1) 5 1 Total Deliveries in Franchise Area $852 $759 $773 $681 $629 Average Revenue Per kWh Sold (Cents) Residential $22.20 $21.90 $21.50 $19.00 $17.80 Commercial and Industrial $17.30 $15.30 $15.60 $13.00 $14.20 For further discussion of the company’s electric operating revenues and its electric results, see “Results of Operations” in Item 7.
O&R’s electric sales and deliveries for the last five years were: Year Ended December 31, 2025 2024 2023 2022 2021 Electric Energy Delivered (millions of kWh) Total deliveries to O&R full service customers 3,541 3,212 2,988 2,973 2,702 Delivery service for retail choice customers 2,234 2,522 2,397 2,580 2,839 Total Deliveries in Franchise Area 5,775 5,734 5,385 5,553 5,541 Electric Energy Delivered ($ in millions) Total deliveries to O&R full service customers $809 $653 $578 $576 $453 Delivery service for retail choice customers 159 198 172 198 223 Other operating revenues (34) 1 9 (1) 5 Total Deliveries in Franchise Area $934 $852 $759 $773 $681 Average Revenue Per kWh Sold (Cents) Residential ¢25.30 ¢22.20 ¢21.90 ¢21.50 ¢19.00 Commercial and Industrial ¢18.80 ¢17.30 ¢15.30 ¢15.60 ¢13.00 For further discussion of the company’s electric operating revenues and its electric results, see “Results of Operations” in Item 7.
Gas CECONY delivers gas to approximately 1.1 million customers in Manhattan, the Bronx, parts of Queens and most of Westchester County. Steam CECONY operates the largest steam distribution system in the United States by producing and delivering approximat ely 15,494 MMlb of steam annually to approximately 1,520 customers in parts of Manhattan.
Gas CECONY delivers gas to approximately 1.1 million customers in Manhattan, the Bronx, parts of Queens and most of Westchester County. Steam CECONY operates the largest steam distribution system in the United States by producing and delivering approximat ely 16,975 MMlb of steam annually to approximately 1,490 customers in parts of Manhattan.
GHG Emissions Reporting Based on the most recent data (2022) published by the U.S. Environmental Protection Agency (EPA), Con Edison estimates that its direct GHG emissions constitute less than 0.1 percent of the nation’s GHG emissions.
GHG Emissions Reporting Based on the most recent data (2022) published by the EPA, Con Edison estimates that its direct GHG emissions constitute less than 0.1 percent of the nation’s GHG emissions.
Steam Peak Demand and Capacity The steam actual hourly peak demand in CECONY’s service area occurs during the winter heating season and during the winter of 2024/2025 (through January 31, 2025) occurred on January 22, 2025 when the actual hourly demand reached approximately 7.1 MMlb per hour.
Steam Peak Demand and Capacity The steam actual hourly peak demand in CECONY’s service area occurs during the winter heating season and during the winter of 2025/2026 (through January 31, 2026) occurred on January 30, 2026 when the actual hourly demand reached approximately 7.01 MMlb per hour.
CON EDISON ANNUAL REPORT 2024 43 The EPA's Transport Rule (also referred to as the Cross-State Air Pollution Rule), which was implemented in January 2015, established a new cap-and-trade program requiring further reductions in air emissions than the Clean Air Intrastate Rule (CAIR) that it replaced.
The EPA's Transport Rule (also referred to as the Cross-State Air Pollution Rule), which was first implemented in January 2015, established a new cap-and-trade program requiring further reductions in air emissions than the Clean Air Intrastate Rule (CAIR) that it replaced.
O&R Electric Operations Electric Facilities O&R’s capitalized costs for utility plant, net of accumulated depreciation, for distribution facilities were $1,359 million and $1,253 million at December 31, 2024 and 2023, respectively. For its transmission facilities, the costs for utility plant, net of accumulated depreciation, were $369 million and $319 million at December 31, 2024 and 2023, respectively.
O&R Electric Operations Electric Facilities O&R’s capitalized costs for utility plant, net of accumulated depreciation, for distribution facilities were $1,482 million and $1,359 million at December 31, 2025 and 2024, respectively. For its transmission facilities, the costs for utility plant, net of accumulated depreciation, were $377 million and $369 million at December 31, 2025 and 2024, respectively.
In July 2022, the NYSPSC issued an order that provides CECONY and O&R with up to a total of $31 million and $5.8 million, respectively, through 2025, for implementation of residential vehicle managed charging programs and administration costs. The NYSPSC authorized CECONY and O&R to recover these costs through surcharge mechanisms.
In July 2022, the NYSPSC issued an order that provided CECONY and O&R with up to a total of $31 million and $5.8 million, respectively, through 2025, for implementation of residential vehicle managed charging programs and administration costs.
At December 31, 2024, the company owned or jointly owned 490 miles of overhead circuits operating at 138, 230, 345 and 500 kV and 760 miles of underground circuits operating at 69, 138 and 345 kV. The compa ny’s 40 transmission substations and 63 area stations are supplied by circuits operated at 69 kV and above.
At December 31, 2025, the company owned or jointly owned 490 miles of overhead circuits operating at 138, 230, 345 and 500 kV and 770 miles of underground circuits operating at 69, 138 and 345 kV. The company’s 40 transmission substations and 63 area stations are supplied by circuits operated at 69 kV and above.
Ownership Interest In-Service Date/Anticipated Base Return on Common Equity (ROE) plus Common Equity Ratio Transmission Owner Transmission Solutions (TOTS) (a) 45.7% 2016 9.5% plus 0.50% = 10% 53% New York Energy Solution (NYES) (b) 45.7% 2023/2025 9.65% plus 1% =10.65% 53% Propel NY Energy (c) 41.7% of New York Transco's share 2030 10.3% plus 1% = 11.3% 53% (a) TOTS is a group of three electric power bulk transmission projects ($217 million total cost) constructed on the New York bulk transmission system to increase transfer capability between upstate and downstate New York.
Ownership Interest In-Service Date/Anticipated Base Return on Common Equity plus incentive Return on Equity (ROE) Common Equity Ratio Transmission Owner Transmission Solutions (TOTS) (a) 45.7% 2016 9.99% plus 0.50% = 10.49% 53% New York Energy Solution (NYES) (b) 45.7% 2023/2025 9.99% plus 0.50% to 1.00% = 10.49% to 10.89% (c) 53% Propel NY Energy (d) 41.7% of New York Transco's share 2030 10.3% plus 1% = 11.3% 53% (a) TOTS is a group of three electric power bulk transmission proje cts ($217 million to tal cost) constructed on the New York bulk transmissi on system to increase transfer capability between upstate and downstate New York.
Since its promulgation, the Good Neighbor Rule has been the subject of litigation in the federal Circuit Courts of Appeals and the U.S. Supreme Court. In June 2024, the U.S. Supreme Court granted a request to stay the Good Neighbor Rule while judicial review over its merits was ongoing in the D.C. Circuit.
The Good Neighbor Rule was the subject of litigation in multiple courts and, in June 2024, the U.S. Supreme Court granted a request to stay the Good Neighbor Rule while judicial review over its merits was ongoing in the D.C. Circuit.
These amounts are subject to approval by the NYSPSC. Electric Vehicles In July 2020, the NYSPSC established light-duty electric vehicle make-ready and other infrastructure programs that included budgets of $290 million and $24 million for CECONY and O&R, respectively, through 2025.
Electric Vehicles In July 2020, the NYSPSC established light-duty electric vehicle make-ready and other infrastructure programs that included budgets of $290 million and $24 million for CECONY and O&R, respectively, through 2025.
O&R’s gas sales and deliveries for the last five years were: Year Ended December 31, 2024 2023 2022 2021 2020 Gas Delivered (MDt) Firm sales Full service 12,516 14,357 15,353 13,998 11,877 Firm transportation 4,623 5,055 6,396 7,584 8,271 Total Firm Sales 17,139 19,412 21,749 21,582 20,148 Interruptible sales 3,712 3,301 3,911 3,821 3,633 Total Gas Delivered to O&R Customers 20,851 22,713 25,660 25,403 23,781 Transportation of customer-owned gas Sales for resale 710 672 673 468 658 Sales to electric generating stations 10 4 10 26 59 Off-system sales 109 20 73 81 19 Total Sales 21,680 23,409 26,416 25,978 24,517 Year Ended December 31, 2024 2023 2022 2021 2020 Gas Delivered ($ in millions) Firm sales Full service $187 $230 $245 $190 $141 Firm transportation 34 38 45 55 62 Total Firm Sales 221 268 290 245 203 Interruptible Sales 7 6 6 6 6 Total Gas Delivered to O&R Customers 228 274 296 251 209 Transportation of customer-owned gas Other operating revenues 45 23 16 9 24 Total Sales $273 $297 $312 $260 $233 Average Revenue Per Dt Sold Residential $15.44 $16.90 $16.49 $14.09 $12.40 General $11.73 $12.64 $13.62 $11.24 $9.51 For further discussion of the company’s gas operating revenues and its gas results, see “Results of Operations” in Item 7.
O&R’s gas sales and deliveries for the last five years were: Year Ended December 31, 2025 2024 2023 2022 2021 Gas Delivered (MDt) Firm sales Full service 16,558 12,516 14,357 15,353 13,998 Firm transportation 5,300 4,623 5,055 6,396 7,584 Total Firm Sales 21,858 17,139 19,412 21,749 21,582 Interruptible sales 3,630 3,712 3,301 3,911 3,821 Total Gas Delivered to O&R Customers 25,488 20,851 22,713 25,660 25,403 Transportation of customer-owned gas Sales for resale 790 710 672 673 468 Sales to electric generating stations 2 10 4 10 26 Off-system sales 164 109 20 73 81 Total Sales 26,444 21,680 23,409 26,416 25,978 Year Ended December 31, 2025 2024 2023 2022 2021 Gas Delivered ($ in millions) Firm sales Full service $277 $187 $230 $245 $190 Firm transportation 41 34 38 45 55 Total Firm Sales 318 221 268 290 245 Interruptible Sales 7 7 6 6 6 Total Gas Delivered to O&R Customers 325 228 274 296 251 Transportation of customer-owned gas Other operating revenues 6 45 23 16 9 Total Sales $331 $273 $297 $312 $260 Average Revenue Per Dt Sold Residential $17.43 $15.44 $16.90 $16.49 $14.09 General $13.43 $11.73 $12.64 $13.62 $11.24 For further discussion of the company’s gas operating revenues and its gas results, see “Results of Operations” in Item 7.
Liability under these laws can be material and may be imposed for contamination from past acts, even though such past acts may have been lawful CON EDISON ANNUAL REPORT 2024 39 at the time they occurred.
Liability under these laws can be material and may be imposed for contamination from past acts, even though such past acts may have been lawful at the time they occurred.
For each of the Companies, the common equity ratio for the last five years was: Common Equity Ratio (Percent of total capitalization) 2024 2023 2022 2021 2020 Con Edison 47.1 49.1 50.9 47.4 48.3 CECONY 46.0 47.9 46.9 47.0 47.9 The credit ratings assigned by Moody’s, S&P and Fitch to the issuer rating and commercial paper rating of Con Edison, and the senior unsecured debt and commercial paper ratings of CECONY and O&R are as follows: Moody's S&P Fitch Con Edison Issuer Rating Baa1 A- BBB+ Commercial Paper P-2 A-2 F2 CECONY Senior Unsecured Debt A3 A- A- Commercial Paper P-2 A-2 F2 O&R Senior Unsecured Debt Baa2 A- A- Commercial Paper P-2 A-2 F2 Credit ratings assigned by rating organizations are expressions of opinion and are not recommendations to buy, sell or hold securities.
See "Liquidity and Capital Resources" in Item 7. 32 CON EDISON ANNUAL REPORT 2025 For each of the Companies, the common equity ratio for the last five years was: Common Equity Ratio (Percent of total capitalization) 2025 2024 2023 2022 2021 Con Edison 48.6 47.1 49.1 50.9 47.4 CECONY 47.8 46.0 47.9 46.9 47.0 The credit ratings assigned by Moody’s, S&P and Fitch to the issuer rating and commercial paper rating of Con Edison, and the senior unsecured debt and commercial paper ratings of CECONY and O&R are as follows: Moody's S&P Fitch Con Edison Issuer Rating Baa1 A- BBB+ Commercial Paper P-2 A-2 F2 CECONY Senior Unsecured Debt A3 A- A- Commercial Paper P-2 A-2 F2 O&R Senior Unsecured Debt Baa1 A- A- Commercial Paper P-2 A-2 F2 Credit ratings assigned by rating organizations are expressions of opinion and are not recommendations to buy, sell or hold securities.
Climate change could affect customer demand for the Companies’ energy services. It might also cause physical damage to the Companies’ facilities and disruption of their operations due to more frequent and more extreme weather. See “The Failure of, or Damage to, the Companies’ Facilities Could Adversely Affect the Companies” in Item 1A.
It might also cause physical damage to the Companies’ facilities and disruption of their operations due to more frequent and more extreme weather. See “The Failure of, or Damage to, the Companies’ Facilities Could Adversely Affect the Companies” in Item 1A.
Steam Supply 33 percent of the steam produced by CECONY in 2024 was supplied by the company’s steam-only generating assets; 46 percent was produced by the company’s steam-electric generating assets, where steam and electricity are primarily cogenerated; and 21 percent was purchased under an agreement with Brooklyn Navy Yard Cogeneration Partners L.P.
Steam Supply 40 percent of the steam produced by CECONY in 2025 was supplied by the company’s steam-only generating assets; 42 percent was produced by the company’s steam-electric generating assets, where steam and electricity are primarily cogenerated; and 18 percent was purchased under an agreement with Brooklyn Navy Yard Cogeneration Partners L.P.
Dielectric fluid reached nearby streets, properties and the New Rochelle Harbor. CECONY, the U.S. Coast Guard, the NYSDEC and other agencies responded to the incident. CECONY stopped the feeder leak on the same day the discharge occurred and has completed the spill recovery and associated cleanup operations. As a result of the discharge, CECONY received third-party damage claims.
CECONY, the U.S. Coast Guard, the NYSDEC and other agencies responded to the incident. CECONY stopped the feeder leak on the same day the discharge occurred and has completed the spill recovery and associated cleanup operations. As a result of the discharge, CECONY received third-party damage claims.
The company has approximately 1,226 MDt of additional natural gas storage capacity available to it at a field in upstate New York, owned and operated by Honeoye, a corporation 71.2 percent owned by Con Edison Transmission and 28.8 percent owned by CECONY. Con Edison Transmission and CECONY are considering strategic alternatives with respect to their investments in Honeoye.
The company has a contract for approximately 1.2 Bcf of additio nal natural gas storage capacity at a field in upstate New York, owned and operated by Honeoye, a corporation 71.2 percent owned by Con Edison Transmission and 28.8 percent owned by CECONY. Con Edison Transmission and CECONY are considering strategic alternatives with respect to their investments in Honeoye.
Con Edison also plans to issue common equity of approximately $1,850 million in 2026 and up to $4,300 million in aggregate during 2027 through 2029, in addition to equity issued under its dividend reinvestment, employee stock purchase and long-term incentive plans.
Con Edison also plans to issue common equity of approximately $1,200 million in 2027 and up to $3,300 million in aggregate during 2028 through 2030, in addition to equity issued under its dividend reinvestment, employee stock purchase and long-term incentive plans.