Biggest changeGAAP Financial Measures for additional disclosure. 25 Table of Contents The following chart presents the 50,000 tpd Project annual cash flow using $1,600/oz gold and an A$1.00:$0.71 exchange rate: The following table provides additional details of the 50,000 tpd Project economics at variable gold price and foreign exchange assumptions: Gold Price and Foreign Exchange Rate Sensitivity Table ($ Millions) Foreign Gold Price Exchange Rate $1,300 $1,400 $1,500 $1,600 $1,700 $1,800 $1,900 ($/A$) NPV 5% IRR NPV 5% IRR NPV 5% IRR NPV 5% IRR NPV 5% IRR NPV 5% IRR NPV 5% IRR 0.74 $214 8.6% $453 12.4% $674 15.5% $911 19.0% $1,144 22.1% $1,372 25.0% $1,589 27.7% 0.71 $304 10.2% $541 14.0% $762 17.3% $999.5† 20.6%† $1,229 23.7% $1,458 26.7% $1,674 29.4% 0.68 $393 11.9% $626 15.6% $851 18.9% $1,085 22.3% $1,313 25.7% $1,543 28.5% $1,758 31.3% † Reflects the assumptions used for the economic analysis in the Mt Todd FS. 26 Table of Contents Key capital expenditures for the 50,000 tpd Project initial and sustaining capital requirements are: Capital Expenditures ($ Millions, except per ounce amount) Initial Sustaining Capital Capital Mining $ 81 $ 531 Process Plant 474 28 Project Services 56 89 Project Infrastructure 45 8 Site Establishment & Early Works 24 — Management, Engineering, EPCM Services 100 — Preproduction Costs 27 — Contingency 86 44 Sub-Total $ 892 $ 700 Asset Sale and Salvage — (37) Total Capital $ 892 $ 663 (1) Total Capital per Payable Ounce of Gold $ 141 $ 105 (1) Note: Amounts may not add to total due to rounding.
Biggest changeGAAP Financial Measures for additional disclosure. 26 Table of Contents The following chart presents the 50,000 tpd Project annual cash flow using $1,800/oz gold and an A$1.00:$0.69 exchange rate: The following table provides additional details of the 50,000 tpd Project economics at variable gold price and foreign exchange assumptions: Gold Price and Foreign Exchange Rate Sensitivity Table ($ Billions) Foreign Gold Price Exchange Rate $1,400 $1,500 $1,600 $1,700 $1,800 $1,900 $2,000 $2,100 $2,200 ($/A$) NPV 5% IRR (%) NPV 5% IRR (%) NPV 5% IRR (%) NPV 5% IRR (%) NPV 5% IRR (%) NPV 5% IRR (%) NPV 5% IRR (%) NPV 5% IRR (%) NPV 5% IRR (%) 0.66 $0.3 9.8 $0.5 13.0 $0.8 16.1 $1.0 19.1 $1.2 22.0 $1.4 24.6 $1.7 27.2 $1.9 29.6 $2.1 32.1 0.69 $0.2 8.1 $0.4 11.4 $0.7 14.6 $0.9 17.5 $1.1† 20.4† $1.3 22.9 $1.6 25.5 $1.8 27.9 $2.0 30.3 0.72 $0.1 6.6 $0.3 9.9 $0.6 13.1 $0.8 15.9 $1.0 18.8 $1.3 21.3 $1.5 23.9 $1.7 26.2 $1.9 28.6 † Reflects the assumptions used for the economic analysis in the Mt Todd FS. 27 Table of Contents Key capital expenditures for the 50,000 tpd Project initial and sustaining capital requirements are: Capital Expenditures ($ Millions, except per ounce amount) Initial Sustaining Capital Capital Mining $ 94 $ 584 Process Plant 561 33 Project Services 57 86 Project Infrastructure 49 8 Site Establishment & Early Works 27 — Management, Engineering, EPCM Services 111 — Preproduction Costs 31 — Contingency 99 48 Sub-Total $ 1,030 $ 759 Asset Sale and Salvage — (43) Total Capital $ 1,030 $ 716 (1) Total Capital per Payable Ounce of Gold (2) $ 163 $ 113 (1) Note: Amounts may not add to total due to rounding.
For a description of the key assumptions, parameters and methods used to estimate mineral reserves and mineral resources included in this Form 10-K, as well as data verification procedures and a general discussion of the extent to which the estimates may be affected by any known environmental, permitting, legal, title, taxation, sociopolitical, marketing or other relevant factors, please review the technical report summary of the Mt Todd FS (as described below) which is included as an exhibit to this Form 10-K. Mt Todd Gold Project, Northern Territory, Australia Summary Disclosure The Company has one material mining property, the Mt Todd gold project located in the Northern Territory of Australia.
For a description of the key assumptions, parameters and methods used to estimate mineral resources and mineral reserves included in this Form 10-K, as well as data verification procedures and a general discussion of the extent to which the estimates may be affected by any known environmental, permitting, legal, title, taxation, sociopolitical, marketing or other relevant factors, please review the technical report summary of the Mt Todd FS (as described below) which is included as an exhibit to this Form 10-K. Mt Todd Gold Project, Northern Territory, Australia Summary Disclosure The Company has one material mining property, the Mt Todd gold project located in the Northern Territory of Australia.
The shaded portion of the table highlights the impact of sorting which reduces the tonnage processed by 10%, increases the processed grade by a similar percentage, and results in cost savings in the grinding, leaching and tailings handling. Years Pit Ore Mined (kt) Waste Mined (kt) Ore Crushed (kt) Crushed Grade (g/t) Contained Ounces (kozs) Ore to CIP (Post Sorting) (kt) CIP Grade (g/t) Contained Ounces (kozs) Gold Produced (kozs) Recovery (%) (1) 7,188 14,066 0 0 0 0 0.00 0 0 0 1 † 18,216 25,904 12,334 1.10 436 11,100 1.21 431 399 92.6% 2 30,578 38,623 17,750 0.88 503 15,975 0.97 497 458 92.1% 3 19,696 63,199 17,750 1.04 594 15,975 1.14 587 542 92.5% 4 15,218 69,774 17,799 0.66 378 16,019 0.73 373 341 91.3% 5 27,591 66,264 17,750 0.79 451 15,975 0.87 445 408 91.7% 6 25,499 74,510 17,823 1.03 591 16,041 1.13 583 539 92.4% 7 13,229 77,291 17,750 0.97 554 15,975 1.06 546 504 92.3% 8 7,779 71,277 17,774 0.69 392 15,997 0.75 386 352 91.2% 9 13,866 59,499 17,774 0.52 295 15,997 0.57 291 261 89.8% 10 14,523 50,082 17,750 0.55 312 15,975 0.60 308 277 90.1% 11 20,830 40,490 17,750 0.61 347 15,975 0.67 343 311 90.7% 12 18,523 13,685 17,774 0.72 410 15,997 0.79 404 370 91.4% 13 11,307 4,388 17,774 0.76 433 15,997 0.83 428 391 91.6% 14 13,829 1,866 17,750 0.79 448 15,975 0.86 442 406 91.7% 15 9,149 412 17,750 0.78 446 16,120 0.85 440 403 91.6% 16 ‡ 0 0 16,710 0.64 344 15,968 0.66 341 310 90.7% 17 ‡ 0 0 2,612 0.54 45 2,612 0.54 45 41 89.8% Total 267,021 671,331 280,375 0.77 6,979 253,673 0.84 6,891 6,313 91.6% Note: Amounts may not add due to rounding. † Six-month startup and commissioning period ahead of full production ‡ Total milled ore includes material from the existing heap leach pad that is processed in years 16 and 17. 28 Table of Contents Mineral Resources and Mineral Reserves Estimates The mineral resources and mineral reserves reported in this section were prepared in accordance with both S-K 1300 standards and CIM Definition Standards.
The shaded portion of the table highlights the impact of ore sorting which reduces the tonnage processed by 10%, increases the processed grade by a similar percentage, and results in cost savings in the grinding, leaching and tailings handling. Years Pit Ore Mined (kt) Waste Mined (kt) Ore Crushed (kt) Crushed Grade (g/t) Contained Ounces (kozs) Ore to CIP (Post Sorting) (kt) CIP Grade (g/t) Contained Ounces (kozs) Gold Produced (kozs) Recovery (%) (1) 7,188 14,066 0 0 0 0 0.00 0 0 0 1 † 18,216 25,904 12,334 1.10 436 11,100 1.21 431 399 92.6% 2 30,578 38,623 17,750 0.88 503 15,975 0.97 497 458 92.1% 3 19,696 63,199 17,750 1.04 594 15,975 1.14 587 542 92.5% 4 15,218 69,774 17,799 0.66 378 16,019 0.73 373 341 91.3% 5 27,591 66,264 17,750 0.79 451 15,975 0.87 445 408 91.7% 6 25,499 74,510 17,823 1.03 591 16,041 1.13 583 539 92.4% 7 13,229 77,291 17,750 0.97 554 15,975 1.06 546 504 92.3% 8 7,779 71,277 17,774 0.69 392 15,997 0.75 386 352 91.2% 9 13,866 59,499 17,774 0.52 295 15,997 0.57 291 261 89.8% 10 14,523 50,082 17,750 0.55 312 15,975 0.60 308 277 90.1% 11 20,830 40,490 17,750 0.61 347 15,975 0.67 343 311 90.7% 12 18,523 13,685 17,774 0.72 410 15,997 0.79 404 370 91.4% 13 11,307 4,388 17,774 0.76 433 15,997 0.83 428 391 91.6% 14 13,829 1,866 17,750 0.79 448 15,975 0.86 442 406 91.7% 15 9,149 412 17,750 0.78 446 16,120 0.85 440 403 91.6% 16 ‡ 0 0 16,710 0.64 344 15,968 0.66 341 310 90.7% 17 ‡ 0 0 2,612 0.54 45 2,612 0.54 45 41 89.8% Total 267,021 671,331 280,375 0.77 6,979 253,673 0.84 6,891 6,313 91.6% Note: Amounts may not add due to rounding. † Six-month startup and commissioning period ahead of full production ‡ Total milled ore includes material from the existing heap leach pad that is processed in years 16 and 17. 29 Table of Contents Mineral Resources and Mineral Reserves Estimates The mineral resources and mineral reserves reported in this section were prepared in accordance with both S-K 1300 standards and CIM Definition Standards.
Vista plans to recover gold in a conventional CIP recovery circuit. Mineral Processing The flowsheet consists of open-circuit primary crushing, closed-circuit secondary crushing, closed-circuit tertiary crushing using HPGR crushers, ore sorting, two-stage grinding, cyclone classification, pre-leach thickening, leach and adsorption, elution electrowinning and smelting, carbon regeneration, tailings detoxification and disposal to conventional tailings storage facility. The flowsheet for the Project is illustrated below. Metallurgical Testing Our metallurgical test work programs have confirmed: (1) ore hardness of the Batman deposit is consistent throughout the deposit and does not change at depth; (2) the selection of HPGR crusher technology as part of the comminution circuit; (3) the selection of ore sorting technology to eliminate low-grade material after crushing and prior to grinding; (4) estimated gold recovery rates based on optimized grind size and leach conditions; and (5) the processing of material from the historical heap leach pad at the end of the proposed mine life. The test work results collated from the 2011 and 2012 testing campaigns and additional metallurgical and process test work conducted in 2016, 2017, 2018, and 2019, together with the process design criteria, were used to develop the process flow sheet and mass balance. 44 Table of Contents Ore Hardness Bond ball mill work indices (“BWi”) were determined at a grind size of P80 of 100 mesh for the various products, namely HPGR crusher, ore-sorting, composite samples and waste material. The test results indicate the following: ● The BWi for the ore sorter feed (plus 5/8” screened HPGR crusher product) was higher than the composite samples prepared from the minus 5/8” screened HPGR crusher product.
Vista plans to recover gold in a conventional CIP recovery circuit. Mineral Processing The flowsheet consists of open-circuit primary crushing, closed-circuit secondary crushing, closed-circuit tertiary crushing using HPGR crushers, ore sorting, two-stage grinding, cyclone classification, pre-leach thickening, leach and adsorption, elution electrowinning and smelting, carbon regeneration, tailings detoxification and disposal to conventional tailings storage facility. The flowsheet for the Project is illustrated below. Metallurgical Testing Our metallurgical test work programs have confirmed: (1) ore hardness of the Batman deposit is consistent throughout the deposit and does not change at depth; (2) the selection of HPGR crusher technology as part of the comminution circuit; (3) the selection of ore sorting technology to eliminate low-grade material after crushing and prior to grinding; (4) estimated gold recovery rates based on optimized grind size and leach conditions; and (5) the processing of material from the historical heap leach pad at the end of the proposed mine life. The test work results collated from the 2011 and 2012 testing campaigns and additional metallurgical and process test work conducted in 2016, 2017, 2018, and 2019, together with the process design criteria, were used to develop the process flow sheet and mass balance. 45 Table of Contents Ore Hardness Bond ball mill work indices (“BWi”) were determined at a grind size of P80 of 100 mesh for the various products, namely HPGR crusher, ore-sorting, composite samples and waste material. The test results indicate the following: ● The BWi for the ore sorter feed (plus 5/8” screened HPGR crusher product) was higher than the composite samples prepared from the minus 5/8” screened HPGR crusher product.
Vista’s drilling discovered a larger Batman Deposit resource by probing deeper with diamond drilling averaging 550 meters in depth. 37 Table of Contents Batman Deposit Drilling History Date Reference Holes (#) Percussion (m) Diamond (m) RC (m) 1988 Truelove 17 1,475 — — 1989 Kenny, Wegmann, Fuccenecco 133 6,263 8,562 3,065 1990 Wegmann, Fuccenecco, Gibbs 122 — 5,060 8,072 1991 Billiton 149 501 202 3,090 1992 Zapopan 18 — 1,375 1,320 1993 Zapopan 16 — — 2,814 1994-1997 Pegasus Gold 170 — — 22,534 1998-2000 General Gold Resources 105 — 7,436 26,365 2007 Vista 25 — 9,883 — 2008 Vista 16 — 8,938 — 2010 Vista 12 — 6,864 — 2011 Vista 7 — 4,480 — 2012 Vista 27 — 17,439 — 2015 Vista 5 — 3,185 — 2016-2017 Vista 4 — 1,635 — 1988-2017 Batman Total 826 8,239 75,059 67,260 Vista Drilling 2012 – 2017 Between the fourth quarter of 2012 and the end of the first quarter of 2017, the Vista exploration program at the Batman Deposit consisted of 22 diamond core drillholes containing 12,530 meters that targeted both infill definitional drilling and step-out drilling. The majority of drilling was angled so as to be approximately perpendicular to the mineralized core.
Vista’s drilling discovered a larger Batman Deposit resource by probing deeper with diamond drilling averaging 550 meters in depth. 38 Table of Contents Batman Deposit Drilling History Date Reference Holes (#) Percussion (m) Diamond (m) RC (m) 1988 Truelove 17 1,475 — — 1989 Kenny, Wegmann, Fuccenecco 133 6,263 8,562 3,065 1990 Wegmann, Fuccenecco, Gibbs 122 — 5,060 8,072 1991 Billiton 149 501 202 3,090 1992 Zapopan 18 — 1,375 1,320 1993 Zapopan 16 — — 2,814 1994-1997 Pegasus Gold 170 — — 22,534 1998-2000 General Gold Resources 105 — 7,436 26,365 2007 Vista 25 — 9,883 — 2008 Vista 16 — 8,938 — 2010 Vista 12 — 6,864 — 2011 Vista 7 — 4,480 — 2012 Vista 27 — 17,439 — 2015 Vista 5 — 3,185 — 2016-2017 Vista 4 — 1,635 — 1988-2017 Batman Total 826 8,239 75,059 67,260 Vista Drilling 2012 – 2017 Between the fourth quarter of 2012 and the end of the first quarter of 2017, the Vista exploration program at the Batman Deposit consisted of 22 diamond core drillholes containing 12,530 meters that targeted both infill definitional drilling and step-out drilling. The majority of drilling was angled so as to be approximately perpendicular to the mineralized core.
Most of the equipment was sold in June 2001 and removed from the mine. In March 2006, Vista acquired the concession rights from the Deed Administrators and surface rights from the Jawoyn Association and entered into a contract with the NT Government. Exploration Licenses Since acquiring the Mt Todd ELs, Vista has conducted an ongoing exploration program that includes prospecting, geologic mapping, rock and soil sampling, geophysical surveys and exploration drilling.
Most of the equipment was sold in June 2001 and removed from the mine. In March 2006, Vista acquired the concession rights from the Deed Administrators and surface access rights from the Jawoyn Association and entered into a contract with the NT Government. Exploration Licenses Since acquiring the Mt Todd ELs, Vista has conducted an ongoing exploration program that includes prospecting, geologic mapping, rock and soil sampling, geophysical surveys and exploration drilling.
No data from the ELs were used in the development of the Mt Todd FS results. Exploration sampling summary: Year Soils Rock Chips 2008 0 164 2009 1,333 45 2010 3,135 224 2011 1,925 79 2012 2,312 295 36 Table of Contents 2013 572 51 2014 2,601 143 2015 841 53 2016 241 27 2017 1,098 78 2018 341 132 2019 313 170 2020 278 9 2021 0 11 2022 60 556 Total Samples 15,050 2,037 Exploration Potential for MLs Based on airborne geophysical survey data, we have identified several magnetic targets within our controlled land holdings surrounding the Batman pit.
No data from the ELs were used in the development of the Mt Todd FS results. Exploration sampling summary: Year Soils Rock Chips 2008 0 164 2009 1,333 45 2010 3,135 224 2011 1,925 79 2012 2,312 295 37 Table of Contents 2013 572 51 2014 2,601 143 2015 841 53 2016 241 27 2017 1,098 78 2018 341 132 2019 313 170 2020 278 9 2021 0 11 2022 60 556 Total Samples 15,050 2,037 Exploration Potential for MLs Based on airborne geophysical survey data, we have identified several magnetic targets within our controlled land holdings surrounding the Batman pit.
Final capital costs to complete the project were AUD232 million (USD181 million). Design capacity was never achieved due to inadequacies in the third and fourth stages of the crushing circuit. A throughput rate of just under 7 Mtpy was achieved by mid-1997; however, problems with the flotation circuit which resulted in reduced recoveries necessitated closure of this circuit.
Final capital costs to complete the project were AUD232 million (USD181 million). Design throughput was never achieved due to inadequacies in the third and fourth stages of the crushing circuit. A throughput rate of just under 7 Mtpy was achieved by mid-1997; however, problems with the flotation circuit which resulted in reduced recoveries necessitated closure of this circuit.
In addition, Katherine offers the necessary support functions that are typically found in a medium-sized city with regard to supplies, accommodations, communications, etc. Planned infrastructure for the site includes the following: ● ammonium nitrate and fuel oil facility; ● mine support facilities (heavy vehicle workshop, lube farm, washdown and tire change, warehouse, fuel farm, mining offices, core storage facility); ● heap leach facility; ● small accommodation camp for occasional contractor use; ● water treatment plant; ● power supply; ● pit dewatering; ● mine services; ● communications; ● gatehouse; and ● expanded existing and additional tailings storage facility. Geological Setting, Mineralization, and Deposit Type Mt Todd is situated within the southeastern portion of the Early Proterozoic Pine Creek Geosyncline.
In addition, Katherine offers the necessary support functions that are typically found in a medium-sized city with regard to supplies, accommodations, communications, etc. Planned infrastructure for the site includes the following: ● ammonium nitrate and fuel oil facility; ● mine support facilities (heavy vehicle workshop, lube farm, washdown and tire change, warehouse, fuel farm, mining offices, core storage facility); ● small accommodation camp for occasional contractor use; ● water treatment plant; ● power supply; ● pit dewatering; ● mine services; ● communications; ● gatehouse; and ● expanded existing and additional tailings storage facility. Geological Setting, Mineralization, and Deposit Type Mt Todd is situated within the southeastern portion of the Early Proterozoic Pine Creek Geosyncline.
The table below presents the estimated mineral resources for the Project. Mt Todd Gold Project – Summary of Gold Mineral Resources based on US$1,300/oz Gold Batman Deposit Heap Leach Pad Quigleys Deposit Total Contained Contained Contained Contained Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) Measured — — — — — — 594 1.15 22 594 1.15 22 Indicated 10,816 1.76 613 — — — 7,301 1.11 260 18,117 1.49 873 Measured & Indicated 10,816 1.76 613 — — — 7,895 1.11 282 18,711 1.49 895 Inferred 61,323 0.72 1,421 — — — 3,981 1.46 187 65,304 0.77 1,608 Notes: ● Measured & indicated resources exclude proven and probable reserves. ● The Point of Reference for the Batman and Quigleys deposits is in situ at the property.
The table below presents the estimated mineral resources for the Project. Mt Todd Gold Project – Summary of Gold Mineral Resource (Exclusive of Gold Mineral Reserves) Based on US$1,300/oz Gold Batman Deposit Heap Leach Pad Quigleys Deposit Total Contained Contained Contained Contained Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) Measured — — — — — — 594 1.15 22 594 1.15 22 Indicated 10,816 1.76 613 — — — 7,301 1.11 260 18,117 1.49 873 Measured & Indicated 10,816 1.76 613 — — — 7,895 1.11 282 18,711 1.49 895 Inferred 61,323 0.72 1,421 — — — 3,981 1.46 187 65,304 0.77 1,608 Notes: ● Measured & indicated mineral resources exclude proven and probable mineral reserves. ● The Point of Reference for the Batman and Quigleys deposits is in situ at the property.
Pit parameters: Mining Cost US$1.50/tonne, Milling Cost US$7.80/tonne processed, G&A Cost US$0.46/tonne processed, G&A/Year 8,201 K US$, Au Recovery, Sulfide 85%, Transition 80%, Oxide 80%, 0.2g-Au/t minimum for resource shell. ● Quigleys: Resources constrained within a US$1,300/oz gold Whittle TM pit shell.
Pit parameters: Mining Cost US$1.50/tonne, Milling Cost US$7.80/tonne processed, G&A Cost US$0.46/tonne processed, G&A/Year 8,201 K US$, Au Recovery, Sulfide 85%, Transition 80%, Oxide 80%, 0.2g-Au/t minimum for resource shell. ● Quigleys: Mineral resources constrained within a US$1,300/oz gold Whittle TM pit shell.
The Point of Reference for the Heap Leach is the physical Heap Leach pad at the property. ● Batman and Quigleys resources are quoted at a 0.40g-Au/t cut-off grade. Heap Leach resources are the average grade of the heap, no cut-off applied. ● Batman: Resources constrained within a US$1,300/oz gold Whittle TM pit shell.
The Point of Reference for the Heap Leach is the physical Heap Leach pad at the property. ● Batman and Quigleys resources are quoted at a 0.40g-Au/t cut-off grade. Heap Leach mineral resources are the average grade of the heap, no cut-off applied. ● Batman: Mineral resources constrained within a US$1,300/oz gold Whittle TM pit shell.
Following completion of assay results, all pulps and reject material were shipped back to the Project site and stored. 41 Table of Contents Comparison of Assay Values between the Database and Source Documents Center of Cell Range in ppm Au Frequency Percent Cumulative (+/- 0.1 ppm Au) Percent -1.2 0 0.00 0.00 -1 0 0.00 0.00 -0.8 1 0.01 0.01 -0.6 0 0.00 0.01 -0.4 0 0.00 0.01 -0.2 3 0.04 0.05 0 8,539 99.88 99.93 0.2 5 0.06 0.99 0.4 0 0.00 99.99 0.6 0 0.00 99.99 0.8 0 0.00 99.99 1 0 0.00 99.99 1.2 1 0.01 100.00 Differences with no rounding or truncation of data The tables show the comparison of the gold grade assays within the database and source documents.
Following completion of assay results, all pulps and reject material were shipped back to the Project site and stored. 42 Table of Contents Comparison of Assay Values between the Database and Source Documents Center of Cell Range in ppm Au Frequency Percent Cumulative (+/- 0.1 ppm Au) Percent -1.2 0 0.00 0.00 -1 0 0.00 0.00 -0.8 1 0.01 0.01 -0.6 0 0.00 0.01 -0.4 0 0.00 0.01 -0.2 3 0.04 0.05 0 8,539 99.88 99.93 0.2 5 0.06 0.99 0.4 0 0.00 99.99 0.6 0 0.00 99.99 0.8 0 0.00 99.99 1 0 0.00 99.99 1.2 1 0.01 100.00 Differences with no rounding or truncation of data The tables show the comparison of the gold grade assays within the database and source documents.
There have been no changes in the mineral reserve estimates since December 31, 2021 because the Company and the relevant qualified persons determined that the same material assumptions and criteria continued to apply as of December 31, 2022, including that the Company used a cutoff grade higher than the economic cutoff grade such that any intervening changes in the underlying economic assumptions were not material and did not require use of a cutoff grade greater than 0.35 g Au/t for mineral reserve estimation purposes. ● The effective date of the mineral reserve estimates under the requirements of NI 43-101 is December 31, 2021.
There have been no changes in the mineral reserve estimates since December 31, 2022 because the Company and the relevant qualified persons determined that the same material assumptions and criteria continued to apply as of December 31, 2023, including that the Company used a cutoff grade higher than the economic cutoff grade such that any intervening changes in the underlying economic assumptions were not material and did not require use of a cutoff grade greater than 0.35 g Au/t for mineral reserve estimation purposes. ● The effective date of the mineral reserve estimates under the requirements of NI 43-101 is December 31, 2023.
We discharged treated water in compliance with the standards. The existing Batman pit has the capacity to contain approximately 11.5 gigaliters of water. At the end of December 2022, the pit contained approximately 0.7 gigaliters of water due to previous dewatering operations.
We have discharged treated water in compliance with the standards. The existing Batman pit has the capacity to contain approximately 11.5 gigaliters of water. At the end of December 2022, the pit contained approximately 0.7 gigaliters of water due to previous dewatering operations.
There have been no changes in the mineral resource estimates since December 31, 2021 because upon review the Company and the relevant qualified persons determined that the same material assumptions and estimates, including all economic parameters for resource estimation purposes, continued to apply as of December 31, 2022. ● The effective date of the Batman Deposit, Heap Leach Pad, and Quigleys Deposit mineral resource estimates under the requirements of NI 43-101 is December 31, 2021. ● Mineral resources that are not mineral reserves have no demonstrated economic viability and do not meet all relevant modifying factors.
There have been no changes in the mineral resource estimates since December 31, 2022 because upon review the Company and the relevant qualified persons determined that the same material assumptions and estimates, including all economic parameters for resource estimation purposes, continued to apply as of December 31, 2023. ● The effective date of the Batman Deposit, Heap Leach Pad, and Quigleys Deposit mineral resource estimates under the requirements of NI 43-101 is December 31, 2023. ● Mineral resources that are not mineral reserves have no demonstrated economic viability and do not meet all relevant modifying factors.
Summary of Comparisons of Historical Assays Historical Assays Au in PPM Differences, Source - Database in PPM Database Source Average 0.79 0.70 0 Std Dev 1.48 1.48 0.01 Count 1171 1171 565 Max 33.44 33.45 0.255 Min 0.005 0.005 -0.29 Median 0.3 0.3 0 Differences > 0.01 ppm Au 20 Differences 4 42 Table of Contents Summary of Comparisons of Vista Assays Vista Assays Au in PPM Differences, Source - Database in PPM Database Source Average 0.79 0.78 0 Std Dev 1.89 1.89 0.02 Count 3262 3262 12 Max 55.37 55.37 0.79 Min 0.005 0.005 -1.07 Median 0.26 0.26 0 Differences > 0.01 ppm Au 3 Differences 6 The Company requires periodic rechecking of assays both within and between laboratories.
Summary of Comparisons of Historical Assays Historical Assays Au in PPM Differences, Source - Database in PPM Database Source Average 0.79 0.70 0 Std Dev 1.48 1.48 0.01 Count 1171 1171 565 Max 33.44 33.45 0.255 Min 0.005 0.005 -0.29 Median 0.3 0.3 0 Differences > 0.01 ppm Au 20 Differences 4 43 Table of Contents Summary of Comparisons of Vista Assays Vista Assays Au in PPM Differences, Source - Database in PPM Database Source Average 0.79 0.78 0 Std Dev 1.89 1.89 0.02 Count 3262 3262 12 Max 55.37 55.37 0.79 Min 0.005 0.005 -1.07 Median 0.26 0.26 0 Differences > 0.01 ppm Au 3 Differences 6 The Company requires periodic rechecking of assays both within and between laboratories.
Differences between Batman and Quigleys mining and metallurgical parameters are due to their individual geologic and engineering characteristics. ● Rex Bryan of Tetra Tech, Inc. is the QP responsible for the Statement of Mineral Resources for the Batman, Heap Leach Pad and Quigleys deposits. ● Thomas Dyer of RESPEC is the QP responsible for developing the resource Whittle TM pit shell for the Batman Deposit. ● The effective date of the Batman Deposit, Heap Leach Pad, and Quigleys Deposit mineral resources estimates under the requirements of SK-1300 is December 31, 2022.
Differences between Batman and Quigleys mining and metallurgical parameters are due to their individual geologic and engineering characteristics. ● Rex Bryan of Tetra Tech, Inc. is the QP responsible for the Statement of Mineral Resources for the Batman, Heap Leach Pad and Quigleys deposits. ● Thomas Dyer of RESPEC is the QP responsible for developing the resource Whittle TM pit shell for the Batman Deposit. ● The effective date of the Batman Deposit, Heap Leach Pad, and Quigleys Deposit mineral resources estimates under the requirements of SK-1300 is December 31, 2023.
The study assumes the equipment will be sold when retired from operations, at an estimated salvage value of $21 million. Fleet operators, along with other employees, are expected to be community based, providing benefits by lower camp-related capital and operating costs. Mining equipment would be maintained through a full maintenance and repair contract with the manufacturer’s authorized dealer.
The study assumes the equipment will be sold when retired from operations, at an estimated salvage value of $24 million. Fleet operators, along with other employees, are expected to be community based, providing benefits by lower camp-related capital and operating costs. Mining equipment would be maintained through a full maintenance and repair contract with the manufacturer’s authorized dealer.
Any future mining will require sufficient surety bonding to fund mine closure. 32 Table of Contents Infrastructure Because Mt Todd was an operating mine, infrastructure exists that reduces initial capital expenditure and significantly reduces capital risk related to infrastructure construction, which has been a major source of capital cost overruns in the mining industry over the last decade.
Any future mining will require sufficient surety bonding to fund mine closure. 33 Table of Contents Infrastructure Because Mt Todd was an operating mine, infrastructure exists that reduces initial capital expenditure and significantly reduces capital risk related to infrastructure construction, which has been a major source of capital cost overruns in the mining industry over the last decade.
All of this work was done under the supervision of a Vista geologist. The following section describes the sample preparation, analyses and security undertaken by Vista through the Mt Todd FS resource update. 39 Table of Contents The diamond drilling program was conducted under the supervision of the geologic staff composed of a chief geologist, several experienced geologists, and a core handling/cutting crew.
All of this work was done under the supervision of a Vista geologist. The following section describes the sample preparation, analyses and security undertaken by Vista through the Mt Todd FS resource update. 40 Table of Contents The diamond drilling program was conducted under the supervision of the geologic staff composed of a chief geologist, several experienced geologists, and a core handling/cutting crew.
Ore is planned to be processed in a comminution circuit consisting of large-scale equipment, including: a gyratory crusher, cone crushers, high pressure grinding roll (“HPGR”) crushers followed by X-ray 43 Table of Contents transmission (“XRT”) and laser sorting, and primary ball mills, followed by VXP Mills, as discussed in greater detail below.
Ore is planned to be processed in a comminution circuit consisting of large-scale equipment, 44 Table of Contents including: a gyratory crusher, cone crushers, high pressure grinding roll (“HPGR”) crushers followed by X-ray transmission (“XRT”) and laser sorting, and primary ball mills, followed by VXP Mills, as discussed in greater detail below.
The improvement in mill feed grade is expected to be approximately 8%, resulting in run-of-mine average mill feed grade of 0.84 g Au/t compared to the life-of-mine Batman Pit mineral reserve grade of 0.79 g Au/t. 45 Table of Contents Gold Recoveries We evaluated gold recoveries using two-stage grinding and a finer product size.
The improvement in mill feed grade is expected to be approximately 8%, resulting in run-of-mine average mill feed grade of 0.84 g Au/t compared to the life-of-mine Batman Pit mineral reserve grade of 0.79 g Au/t. 46 Table of Contents Gold Recoveries We evaluated gold recoveries using two-stage grinding and a finer product size.
The mine plan in the Mt Todd FS includes both proven and probable mineral reserves and results in estimated total recovered gold of 6.31 million ounces. 29 Table of Contents The table below presents the estimated mineral reserves for the Project. Mt Todd Gold Project – Summary of Gold Mineral Reserves based on 50,000 tpd, 0.35 g Au/t cut-off and $1,125 per Ounce Pit Design Batman Deposit Heap Leach Pad Total Contained Contained Contained Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) Proven 81,277 0.84 2,192 — — — 81,277 0.84 2,192 Probable 185,744 0.76 4,555 13,354 0.54 232 199,098 0.75 4,787 Proven & Probable 267,021 0.79 6,747 13,354 0.54 232 280,375 0.77 6,979 Economic analysis conducted only on proven and probable mineral reserves.
The mine plan in the Mt Todd FS includes both proven and probable mineral reserves and results in estimated total recovered gold of 6.31 million ounces. 30 Table of Contents The table below presents the estimated mineral reserves for the Project. Mt Todd Gold Project – Summary of Gold Mineral Reserves based on 50,000 tpd, 0.35 g Au/t cut-off and $1,500 per Ounce Pit Design Batman Deposit Heap Leach Pad Total Contained Contained Contained Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) (000s) (g Au/t) (000s) Proven 81,277 0.84 2,192 — — — 81,277 0.84 2,192 Probable 185,744 0.76 4,555 13,354 0.54 232 199,098 0.75 4,787 Proven & Probable 267,021 0.79 6,747 13,354 0.54 232 280,375 0.77 6,979 Economic analysis conducted only on proven and probable mineral reserves.
Two diamond drillholes were drilled at Quigleys. Despite determining that the gold potential of the reefs in the area was promising, AOM ceased work around Mt Todd. 34 Table of Contents The Arafura Mining Corporation, CRA Exploration, and Marriaz Pty Ltd all explored the Mt Todd area at different times between 1975 and 1983.
Two diamond drillholes were drilled at Quigleys. Despite determining that the gold potential of the reefs in the area was promising, AOM ceased work around Mt Todd. 35 Table of Contents The Arafura Mining Corporation, CRA Exploration, and Marriaz Pty Ltd all explored the Mt Todd area at different times between 1975 and 1983.
(2) Total Cash Costs is a non-U.S. GAAP financial measure; see Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations – Non-U.S. GAAP Financial Measures for additional disclosure. 27 Table of Contents In November 2020, we modified our agreement with the Jawoyn Association.
(2) Total Cash Costs is a non-U.S. GAAP financial measure; see Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations – Non-U.S. GAAP Financial Measures for additional disclosure. 28 Table of Contents In November 2020, we modified our agreement with the Jawoyn Association.
The feasibility study was conducted by a joint venture between Bateman Kinhill and Kilborne (“BKK”) and was completed in June 1995. 35 Table of Contents The Pegasus board approved the project on August 17, 1995 and awarded an EPCM contract to BKK in October 1995. Commissioning commenced in November 1996.
The feasibility study was conducted by a joint venture between Bateman Kinhill and Kilborne (“BKK”) and was completed in June 1995. 36 Table of Contents The Pegasus board approved the project on August 17, 1995 and awarded an EPCM contract to BKK in October 1995. Commissioning commenced in November 1996.
The mineralized zones have been defined by wireframes which are used to constrain the higher grades for the resource estimation. The majority of drilling was angled so as to be approximately perpendicular to the mineralized 38 Table of Contents core. This orientation more accurately transects the true thickness of the mineralization.
The mineralized zones have been defined by wireframes which are used to constrain the higher grades for the resource estimation. The majority of drilling was angled so as to be approximately perpendicular to the mineralized 39 Table of Contents core. This orientation more accurately transects the true thickness of the mineralization.
The 33 Table of Contents Burrell Creek Formation is overlain by interbedded greywackes, mudstones, tuffs, minor conglomerates, mafic to intermediate volcanics and banded ironstone of the Tollis Formation. The Burrell Creek Formation and Tollis Formation comprise the Finniss River Group. The Finniss River Group strata have been folded about northerly trending F1 fold axes.
The 34 Table of Contents Burrell Creek Formation is overlain by interbedded greywackes, mudstones, tuffs, minor conglomerates, mafic to intermediate volcanics and banded ironstone of the Tollis Formation. The Burrell Creek Formation and Tollis Formation comprise the Finniss River Group. The Finniss River Group strata have been folded about northerly trending F1 fold axes.
The Mt Todd FS is not incorporated by reference into this annual report on Form 10-K. Certain capitalized terms in this section not otherwise defined have the meanings ascribed to them in the Mt Todd FS. 23 Table of Contents Project Location and Access Mt Todd is located 56 kilometers by road northwest of Katherine, NT, Australia, and approximately 290 kilometers by road southeast of Darwin, NT.
The Mt Todd FS is not incorporated by reference into this annual report on Form 10-K. Certain capitalized terms in this section not otherwise defined have the meanings ascribed to them in the Mt Todd FS. Project Location and Access Mt Todd is located 56 kilometers by road northwest of Katherine, NT, Australia, and approximately 290 kilometers by road southeast of Darwin, NT.
Risk Factors.” There was no change in reserve estimates as of December 31, 2022 compared to December 31, 2021 as the same material assumptions and criteria were determined to continue to apply to the reserve estimates and there was no depletion of reserves in the fiscal year ending December 31, 2022 as the Mt.
Risk Factors.” There was no change in mineral reserve estimates as of December 31, 2023 compared to December 31, 2022 as the same material assumptions and criteria were determined to continue to apply to the mineral reserve estimates and there was no depletion of mineral reserves in the fiscal year ending December 31, 2023 as Mt.
Pegasus progressively increased their shareholding until they acquired full ownership of Zapopan in July 1995. Historical preliminary studies (not S-K 1300 or NI 43-101 compliant) for Phase I, a heap leach operation which focused predominately on the oxide portion of the deposit, commenced during 1992 culminating in an engineering, procurement, construction management (“EPCM”) award to Minproc in November of that year.
Pegasus progressively increased their shareholding until they acquired full ownership of Zapopan in July 1995. Historical preliminary studies (not S-K 1300 or NI 43-101 compliant) for Phase I, a heap leach operation which focused predominately on the oxide portion of the deposit, commenced during 1992 culminating in an engineering, procurement, construction management (“EPCM”) award to Minproc Engineers Pty.
There was no change in resource estimates as of December 31, 2022 compared to December 31, 2021 as the same material assumptions and criteria were determined to continue to apply to the resource estimates and there was no conversion of resources into reserves in the fiscal year ending December 31, 2022.
There was no change in mineral resource estimates as of December 31, 2023 compared to December 31, 2022 as the same material assumptions and criteria were determined to continue to apply to the mineral resource estimates and there was no conversion of mineral resources into mineral reserves in the fiscal year ending December 31, 2023.
Existing mining infrastructure items include: ● a tailings storage facility with capacity for approximately 80 million tonnes of additional material; ● a fresh water storage reservoir that would receive a two-meter dam raise and would harvest stormwater expected to be sufficient to provide process water for year-round operations for a 50,000 tpd operation; ● a natural gas pipeline at site that can supply sufficient natural gas to meet the Project’s energy requirements which, coupled with the planned power generating plant, would save considerably on Project operating costs compared to grid-supplied power; ● a paved road to site; and ● current electrical connection to the NT electric grid. In addition, we expect reduced earthworks costs due to the process plant location being the same as the previous process plant, which has already been cleared and graded. Other benefits of Mt Todd’s NT location include: ● the Stuart highway – the main North / South highway in the NT is less than 10 kilometers from the Project site; ● rail line parallel to the Stuart highway; and ● the regional center of Katherine (population approximately 12,000) less than 40 kilometers from site and the NT capital of Darwin less than 290 kilometers from the Project site, which has port access. The area has both historical and current mining activity and therefore a portion of the skilled workforce should be able to be sourced locally.
Existing mining infrastructure items include: ● a tailings storage facility with capacity for approximately 80 million tonnes of additional material; ● a fresh water storage reservoir that would receive a two-meter dam raise and would harvest stormwater expected to exceed process water requirements for year-round operations for a 50,000 tpd operation; ● a natural gas pipeline at site that can supply sufficient natural gas to meet the Project’s energy requirements which, coupled with the planned third-party-operated power generating plant, would save considerably on Project operating costs compared to grid-supplied power; ● a paved road to site; and ● current electrical connection to the NT electric grid. In addition, we expect reduced earthworks costs due to the process plant location being the same as the previous process plant, which was cleared and graded at the time of original construction. Other benefits of Mt Todd’s location in the NT include: ● the Stuart highway – the main North / South highway in the NT is less than 10 kilometers from the Project site; ● rail line parallel to the Stuart highway; and ● the regional center of Katherine (population approximately 12,000) 56 kilometers from site and the NT capital of Darwin approximately 290 kilometers from the Project site, which has port access. The area has both historical and current mining activity and therefore a portion of the skilled workforce should be able to be sourced locally.
The companion report is referenced herein for informational purposes only. The technical data and economic conclusions of these reports are materially identical, with differences in the formatting of the reports and details of certain assumptions resulting only from the respective disclosure requirements of S-K 1300 and NI 43-101.
The companion report is referenced herein for informational purposes only and is not incorporated herein by reference. The technical data and economic conclusions of these reports are materially identical, with differences in the formatting of the reports and details of certain assumptions resulting only from the respective disclosure requirements of S-K 1300 and NI 43-101.
Final approval was given in September 2014. The Jawoyn people have been consulted with and involved in the planning of the Project.
Final approval was given in September 2014. The Jawoyn Association have been consulted with and involved in the planning of the Project.
Vista expects to incur expenditures of approximately $2,100 for its Mt Todd site maintenance and environmental stewardship activities.
Vista expects to incur expenditures of approximately $2,200 for its Mt Todd site maintenance and environmental stewardship activities.
Subsequently, high reagent consumption, as a result of cyanide soluble copper minerals, further hindered efforts to reach design production. Operating costs were above those predicted in the feasibility study. The spot price of gold deteriorated from above USD400 in early 1996 to below USD300 per ounce at the end of 1997.
Subsequently, high reagent consumption, as a result of cyanide soluble copper minerals, further hindered efforts to reach design gold production. Operating costs were above those predicted in the feasibility study. The spot price of gold deteriorated from above USD$400 in early 1996 to below USD$300 per ounce at the end of 1997.
The reports were prepared by Sabry Abdel Hafez, Ph.D., P.Eng.; Rex Clair Bryan, Ph.D., SME RM; Thomas L. Dyer, P.E., SME RM; Amy Hudson, Ph.D., CPG, REM; April Hussey, P.E.; Chris Johns, M.Sc., P.Eng.; Max Johnson, P.E.; Deepak Malhotra, Ph.D., SME RM; Zvonimir Ponos, BE, MIEAust, CPeng, NER; Vicki J.
The reports were prepared by Maurie Marks, P.Eng.; Rex Clair Bryan, Ph.D., SME RM; Thomas L. Dyer, P.E., SME RM; Amy L. Hudson, Ph.D., CPG, SME RM; April Hussey, P.E.; Chris Johns, M.Sc., P.Eng.; Max Johnson, P.E.; Deepak Malhotra, Ph.D., SME RM; Zvonimir Ponos, BE, MIEAust, CPeng, NER; Vicki J.
The Phase I project was predicated upon a 4 million tonne per year (“Mtpy”) heap leach plant, which came on stream in late 1993.
Ltd. in November of that year. The Phase I project was predicated upon a 4 million tonne per year (“Mtpy”) heap leach plant, which came on stream in late 1993.
Surface elevations are approximately 130 to 160 meters above sea level in the area of the previous and planned mine plant site and waste rock dumps. Project Stage The Mt Todd gold project is a development stage property with proven and probable mineral reserves. 24 Table of Contents Feasibility Study Results The Mt Todd FS evaluates a 50,000 tpd project (“50,000 tpd Project”) that optimizes payable gold, capital efficiency, operating costs and net present value (“NPV”). The 50,000 tpd Project highlights include: ● estimated proven and probable mineral reserves of 6.98 million ounces of gold (280 Mt at 0.77 g Au/t) at a cut-off grade of 0.35 g Au/t (1)(2) ; ● average annual production of 395,000 ounces of gold over the 16-year mine life, including average annual production of 479,000 ounces of gold per year during the first seven years of operations following commissioning and ramp-up; ● life of mine average cash costs of $817 per ounce, including average cash costs of $752 per ounce during the first seven years of operations following commissioning and ramp-up; ● a 16-year operating life; ● initial capital requirements of $892 million which assume an owner-operated mining fleet, power generated on-site by a third-party, and a locally based employee workforce; ● after-tax NPV 5% of $999.5 million and internal rate of return (“IRR”) of 20.6% at a gold price of $1,600 per ounce and an AUD:USD exchange rate of 0.71; and ● after-tax NPV 5% of $1.7 billion and IRR of 29.4% at a price of $1,900 per ounce of gold and an AUD:USD exchange rate of 0.71 based on the Gold Price and Foreign Exchange Sensitivity Table below. (1) Note to investors: Proven and probable mineral reserves are estimated in accordance with S-K 1300 and CIM Definition Standards.
Surface elevations are approximately 130 to 160 meters above sea level in the area of the previous and planned mine plant site and waste rock dumps. Project Stage The Mt Todd gold project is a development stage property with proven and probable mineral reserves. 25 Table of Contents Feasibility Study Results The Mt Todd FS evaluates a 50,000 tpd project (“50,000 tpd Project”) that optimizes payable gold, capital efficiency, operating costs and net present value (“NPV”). The 50,000 tpd Project highlights include: ● estimated proven and probable mineral reserves of 6.98 million ounces of gold (280 Mt at 0.77 g Au/t) using a gold price of $1,500 for the reserve estimate and a cut-off grade of 0.35 g Au/t (1)(2) ; ● average annual production of 395,000 ounces of gold over the 16-year mine life, including average annual production of 479,000 ounces of gold per year during the first seven years of operations following commissioning and ramp-up; ● life of mine average cash costs of $913 per ounce, including average cash costs of $845 per ounce during the first seven years of operations following commissioning and ramp-up (3) ; ● a 16-year operating life; ● initial capital requirements of $1.03 billion which assume an owner-operated mining fleet, power generated on-site by a third-party, and a locally based employee workforce; ● after-tax NPV 5% of $1.13 billion and IRR of 20.4% at a gold price of $1,800 per ounce and an AUD:USD exchange rate of 0.69; and ● after-tax NPV 5% of $1.78 billion and IRR of 27.9% at a price of $2,100 per ounce of gold and an AUD:USD exchange rate of 0.69 based on the Gold Price and Foreign Exchange Sensitivity Table below. (1) Note to investors: Proven and probable mineral reserves are estimated in accordance with S-K 1300 and CIM Definition Standards.
(“Pegasus”), the NT Government, and the Jawoyn Association, we acquired the concession rights and access to Mt Todd. Also in 2006, through an agreement with the NT Government, we established the rights and obligations of Vista and the NT Government with respect to Mt Todd site care and maintenance and potential future development.
Also in 2006, through an agreement with the NT Government, we established the rights and obligations of Vista and the NT Government with respect to Mt Todd site care and maintenance and potential future development.
Should a deposit be discovered on the ELs, the portion of the related EL would have to be converted to an ML before mining operations could start. 31 Table of Contents Mt Todd Land Holdings of Vista Gold Australia Estimated Holding Requirements Annual Rent & Annual Work Annual Surface Location Admin Fees Requirement Expenditure/ Area Description Location Date/ (thousands (thousands Technical Mineral Licenses (Km 2 ) (UTM) Grant Date Renewal Date of A$) of A$) Reports Due MLN 1070 39.8 Mining License Block March 5, 1993 March 4, 2043 88 (due March 4) N/A May 4 MLN 1071 13.3 centered at March 5, 1993 March 4, 2043 29 (due March 4) N/A May 4 MLN 1127 0.8 approximately March 5, 1993 March 4, 2043 2 (due March 4) N/A May 4 MLN 31525 1.6 188555E, 435665N September 4, 2017 September 3, 2042 4 (due September 3) N/A May 4 Subtotal 55.4 123 - Estimated Holding Requirements Annual Rent & Annual Work Annual Surface Location Admin Fees Requirement Expenditure/ Area Description Location Date/ (thousands (thousands Technical Exploration Licenses (Km 2 ) (UTM) Grant Date Renewal Date of A$) of A$) Reports Due EL29882 556 Centered at approximately 189100E, 84520000N September 16, 2013 September 15, 2023 39 (due September 15) 125 May 14 EL29886 595 Centered at approximately 200300E, 8452000N September 16, 2013 September 15, 2023 45 (due September 15) 77 May 14 EL30898 187 Centered at approximately 176100E, 8428700N May 3, 2016 May 2, 2024 13 (due May 2) 12 May 14 EL32004 163 Centered at approximately 164000E, 8430550N November 21, 2019 November 20, 2025 4 (due November 20) 30 May 14 ELA32005 149 Centered at approximately 160180E, 8445150N Under application Under application Under application Under application Under application Subtotal 1,650 101 244 Totals A$ 224 244 Totals US$ (exchange rate of A$1.00 = $0.682 on December 31, 2022) 153 166 The surface land in the area of the contiguous MLs and ELs (excluding EL 32004) is freehold land owned by the Jawoyn Association.
Should a deposit be discovered on the ELs, the portion of the related EL would have to be converted to an ML before mining operations could start. 32 Table of Contents Mt Todd Land Holdings of Vista Gold Australia Estimated Holding Requirements Annual Rent & Annual Work Annual Surface Location Admin Fees Requirement Expenditure/ Area Description Location Date/ (thousands (thousands Technical Mineral Licenses (Km 2 ) (UTM) Grant Date Renewal Date of A$) of A$) Reports Due MLN 1070 39.8 Mining License Block March 5, 1993 March 4, 2043 96 (due March 4) N/A May 4 MLN 1071 13.3 centered at March 5, 1993 March 4, 2043 32 (due March 4) N/A May 4 MLN 1127 0.8 approximately March 5, 1993 March 4, 2043 2 (due March 4) N/A May 4 MLN 31525 1.6 188555E, 435665N September 4, 2017 September 3, 2042 4 (due September 3) N/A May 4 Subtotal 55.4 134 - Estimated Holding Requirements Annual Rent & Annual Work Annual Surface Location Admin Fees Requirement Expenditure/ Area Description Location Date/ (thousands (thousands Technical Exploration Licenses (Km 2 ) (UTM) Grant Date Renewal Date of A$) of A$) Reports Due EL29882 555.5 Centered at approximately 189100E, 84520000N September 16, 2013 September 15, 2025 43 (due September 15) 328 May 14 EL29886 594.6 Centered at approximately 200300E, 8452000N September 16, 2013 September 15, 2025 48 (due September 15) 130 May 14 EL30898 186.7 Centered at approximately 176100E, 8428700N May 3, 2016 May 2, 2024 14 (due May 2) 13 May 14 EL32004 95.3 Centered at approximately 164000E, 8430550N November 21, 2019 November 20, 2025 6 (due November 20) 4 May 14 ELA32005 149.2 Centered at approximately 160180E, 8445150N Under application Under application Under application Under application Under application Subtotal 1,581.3 111 475 Totals A$ 245 475 Totals US$ (exchange rate of A$1.00 = $0.681 on December 31, 2023) 167 323 The surface land in the area of the contiguous MLs and ELs (excluding EL 32004) is freehold land owned by the Jawoyn Association.
Access is by existing paved public roads and approximately four kilometers of paved private road. We control and maintain the private paved road. The area has a sub-tropical climate with a distinct wet season and dry season. The area receives most of its rainfall between the months of January and March. Temperatures are moderate, allowing for year-round mining operations.
Access is by existing paved public roads and approximately four kilometers of paved private road. We control and maintain the private paved road. 24 Table of Contents The area has a sub-tropical climate with a distinct wet season and dry season. The area receives most of its rainfall between the months of January and March.
The only exception to this was when a portion of the remaining core had been flagged for use in the ongoing metallurgical test work. The bagged samples had sample tags placed both inside and on the outside of the sample bags.
The only exception to this was when a portion of the remaining core had been flagged for use in the ongoing metallurgical test work. The bagged samples had sample tags placed both inside and on the outside of the sample bags. The individual samples were grouped into “lots” for submission to Northern Australian Laboratories Pty. Ltd.
The topography is relatively flat. The tenements encompass a variety of habitats forming part of the northern Savannah woodland region, which is characterized by eucalypt woodland with tropical grass understories.
Temperatures are moderate, allowing for year-round mining operations. The topography is relatively flat. The tenements encompass a variety of habitats forming part of the northern Savannah woodland region, which is characterized by eucalypt woodland with tropical grass understories.
Todd Gold Project is in the development stage The tables below show the resource classification criteria and variogram parameters for the Batman resource model. 30 Table of Contents Property Holdings In 2006, through an agreement with Pegasus Gold Australia Pty. Ltd.
Todd is in the development stage. The tables below show the resource classification criteria and variogram parameters for the Batman resource model. 31 Table of Contents Property Holdings In 2006, through an agreement with Pegasus Gold Australia Pty. Ltd. (“Pegasus”), the NT Government, and the Jawoyn Association, we acquired the concession rights and access to Mt Todd.
Dyer, P.E., is the QP responsible for reporting the Batman Deposit Proven and Probable reserves. ● Batman deposit reserves are reported using a 0.35 g Au/t cutoff grade. ● Deepak Malhotra is the QP responsible for reporting the heap-leach pad reserves. ● Because all the heap-leach pad reserves are to be fed through the mill, these reserves are reported without a cutoff grade applied. ● The reserves point of reference is the point where material is fed into the mill. ● The effective date of the mineral reserve estimates under the requirements of S-K 1300 is December 31, 2022.
A US$ 1,500/oz-Au pit shell was used. ● Deepak Malhotra is the QP responsible for reporting the heap-leach pad mineral reserves. ● Because all the heap-leach pad reserves are to be fed through the mill, these reserves are reported without a cutoff grade applied. ● The mineral reserves point of reference is the point where material is fed into the mill. ● The effective date of the mineral reserve estimates under the requirements of S-K 1300 is December 31, 2023.
In 2017, the latter agreement was extended through the end of 2023 and the Company has requested an additional extension. Total land holdings controlled by Vista Gold Australia are approximately 1,705 Km 2 .
The latter agreement was extended during 2017 through the end of 2023 and further extended during 2023 through December 31, 2029 with the option for an additional three-year extension. Total land holdings controlled by Vista Gold Australia are approximately 1,637 Km 2 .
Business – Cautionary Note to Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Mineral Reserves” in this annual report on Form 10-K for additional information. Key statistics of the 50,000 tpd Project are presented in the table below: Years 1-7 (1) Life of Mine (16 years) (2) Average Plant Feed Grade (g Au/t) (3) 1.01 0.84 Average Annual Gold Production (koz) 479 395 Payable Gold Total (koz) 3,353 6,313 Average Recovery (%) 92.2 % 91.6 % Cash Costs ($/oz) (4) $ 752 $ 817 AISC ($/oz) (5) $ 860 $ 928 Strip Ratio (waste:ore) 2.77 2.51 Initial Capital ($ millions) $ 892 After-tax NPV 5% ($ millions) $ 999.5 After-tax IRR 20.6 % After-tax Payback (Months) 47 Note: Table economics presented using $1,600/oz gold and a A$1.00 :$0.71 exchange.
GAAP Financial Measures for additional disclosure. Key statistics of the 50,000 tpd Project are presented in the table below: Years 1-7 (1) Life of Mine (16 years) (2) Average Plant Feed Grade (g Au/t) (3) 1.01 0.84 Average Annual Gold Production (koz) 479 395 Payable Gold Total (koz) 3,353 6,313 Average Recovery (%) 92.2 % 91.6 % Cash Costs ($/oz) (4) $ 845 $ 913 AISC ($/oz) (5) $ 961 $ 1,034 Strip Ratio (waste:ore) 2.77 2.51 Initial Capital ($ billions) $ 1.03 After-tax NPV 5% ($ billions) $ 1.13 After-tax IRR 20.4 % After-tax Payback (years) 4 Note: Table economics presented using $1,800/oz gold and a A$1.00 :$0.69 exchange.
Rozelle, Senior Vice President of Vista. Mr. Rozelle is a qualified person as defined by S-K 1300 and NI 43-101.
Rozelle (PG, member AIPG), a technical consultant. Mr. Rozelle is a qualified person as defined by S-K 1300 and NI 43-101.
The power plant will be owned, operated, and provide power to the Project on a dedicated contract. The following table presents a breakdown of 50,000 tpd Project operating costs. Operating Cost First 7 Years Life of Mine Cost Per ore tonne Per ore tonne processed Per ounce processed Per ounce Mining $ 8.52 $ 316 $ 6.79 $ 302 Processing 9.39 348 9.44 419 Site General and Administrative 1.06 39 0.99 44 Jawoyn Royalty (1) 0.86 32 0.72 32 Water Treatment 0.26 10 0.29 13 Tailings Management 0.08 3 0.08 4 Refining Costs (1) 0.09 3 0.08 3 Total Cash Costs (2) $ 20.28 $ 752 $ 18.40 $ 817 Note: Table may not add to total due to rounding (1) Jawoyn Royalty (as defined below) and refining costs calculated at $1,600 per ounce gold and an A$1.00 : $0.71 exchange rate.
The power plant will be owned, operated, and provide power to the Project on a dedicated contract. The following table presents a breakdown of 50,000 tpd Project operating costs. Operating Cost First 7 Years Life of Mine Cost Per ore tonne Per ore tonne processed Per ounce processed Per ounce Mining $ 9.61 $ 356 $ 7.68 $ 341 Processing 10.17 377 10.21 453 Site General and Administrative 1.11 41 1.05 46 Royalties (1) 1.46 54 1.16 52 Water Treatment 0.27 10 0.30 13 Tailings Management 0.09 3 0.09 4 Refining Costs (1) 0.10 4 0.08 4 Total Cash Costs (2) $ 22.80 $ 845 $ 20.57 $ 913 Note: Table may not add to total due to rounding (1) Royalties (as defined below) and refining costs calculated at $1,800 per ounce gold and an A$1.00 : $0.69 exchange rate.
The sealed crates were stacked outside the core logging shed until picked up for transport. The following laboratories have been used for sample preparation, analyses, and check assays: Laboratory Address Purpose Abbreviation Certifications ALS | Minerals 31 Denninup Way Malaga, WA 6090 Main assay analyses ALS ISO:9001:2008 and ISO 17025 Certified ALS | Minerals 13 Price St Alice Springs, NT 0870 Sample Preparation ALS Alice Springs ISO 9001:2008 and ISO 17025 Certified Genalysis Laboratory Services (Intertek Group) 15 Davison St Maddington, WA 6109 Check Analyses Genalysis Unable to verify North Australian Laboratories Pty Ltd (“NAL”) MLN 792 Eleanor Rd Pine Creek, NT 0847 Alternative assay analyses NAL ISO 17025 Certified NT Environmental Laboratories (Intertek Group) 3407 Export Dr Berrimah, NT 0828 Check Analyses NTEL ISO 17025 40 Table of Contents Vista is completely independent of each of the above listed analytical testing entities, other than the engagement of said entities as a service provider. Each of the laboratories listed follow their own quality controls based on international standards.
The sealed crates were stacked outside the core logging shed until picked up for transport. The following laboratories have been used for sample preparation, analyses, and check assays: Laboratory Address Purpose Abbreviation Certifications ALS | Minerals 31 Denninup Way Malaga, WA 6090 Main assay analyses ALS ISO:9001:2008 and ISO 17025 Certified ALS | Minerals 13 Price St Alice Springs, NT 0870 Sample Preparation ALS Alice Springs ISO 9001:2008 and ISO 17025 Certified Genalysis Laboratory Services (Intertek Group) 15 Davison St Maddington, WA 6109 Check Analyses Genalysis Unable to verify North Australian Laboratories Pty.
The completion of this study is expected in the first quarter of 2023. The strategic process with CIBC Capital Markets is ongoing and remains a top priority. Vista reduced its recurring costs in 2022, and reducing costs and maximizing effectiveness continue to be high priorities in 2023.
The studies will focus on a strategy of scalable development, allowing for throughput expansion or mine-life extension. The strategic process with CIBC Capital Markets is ongoing and remains a top priority. Vista reduced its recurring costs in 2023, and reducing costs and maximizing effectiveness continue to be high priorities in 2024.
The combined GPR range is now from 1.125% to 3.0% and is reflected in the table above. The life of mine production schedule contemplates 280.4 million tonnes of ore containing an estimated 6.98 million ounces of gold at an average grade of 0.77 g Au/t to be processed over a 16-year operating life of the Project.
Pursuant to the terms of the Royalty Agreement, Vista granted Wheaton a royalty in the amount of 1% of gross revenue from the sale or disposition of minerals from the Project, subject to adjustments in certain circumstances. Together, the Jawoyn Royalty and the royalty with Wheaton Precious Metals Corp. comprise the Royalties in the Mt Todd FS. The life of mine production schedule contemplates 280.4 million tonnes of ore containing an estimated 6.98 million ounces of gold at an average grade of 0.77 g Au/t to be processed over a 16-year operating life of the Project.
(“Vista Gold Australia”). Technical Report Summary The 2022 feasibility study for Mt Todd is the technical report summary, prepared pursuant to S-K 1300, that was filed on EDGAR on February 24, 2022 and is entitled “S-K 1300 Technical Report Summary - Mt Todd Gold Project - 50,000 tpd Feasibility Study – Northern Territory, Australia” with an effective date of December 31, 2022 and an issue date of February 9, 2022, as amended February 7, 2023 (the “Mt Todd FS”).
(“Vista Gold Australia”). Technical Report Summary The 2024 feasibility study for Mt Todd is the technical report summary, prepared pursuant to S-K 1300, attached as an exhibit to this Annual Report on Form 10-K and is entitled “S-K 1300 Technical Report Summary - Mt Todd Gold Project - 50,000 tpd Feasibility Study – Northern Territory, Australia” with an effective date of March 12, 2024 (the “Mt Todd FS”). A companion feasibility study for Canadian purposes, pursuant to NI 43-101, will also be filed in accordance with NI 43-101 disclosure standards on SEDAR+ on or before April 27, 2024.
The MMP was approved in June 2021 and is in the process of being amended to align with the larger-scale design in the Mt Todd FS.
The MMP was approved in June 2021 and is in the process of being amended to align with the larger-scale design in the Mt Todd FS. The changes to the pit, tailings storage facilities, and waste rock dump designs have been referred to the NT EPA as required under the Environmental Protection Act 2019 for its consideration.
Rozelle, Senior Vice President of Vista and a qualified person as defined by S-K 1300 and NI 43-101, has verified the data disclosed in this document, including sampling, analytical and test data underlying the information contained in the disclosure. Sample Security NAL is the primary laboratory we use for analysis of drill core assays.
Rozelle (PG, member AIPG), a technical consultant, and a qualified person as defined by S-K 1300 and NI 43-101, has verified the data disclosed in this document, including sampling, analytical and test data underlying the information contained in the disclosure. Mr. Rozelle does not have an ownership, royalty, or other interest in the property.
The changes to the waste rock dump design have been referred to the NT EPA as required under the Environmental Protection Act 2019 for its consideration. 46 Table of Contents Environmental, Social and Community Factors A number of environmental studies have been conducted at Mt Todd in support of the EIS and as required for environmental and operational permits.
The NT EPA referral review has been suspended at our request while we respond to questions raised by the Aboriginal Areas Protection Authority regarding the increased area of the footprint of the new facilities. 47 Table of Contents Environmental, Social and Community Factors A number of environmental studies have been conducted at Mt Todd in support of the EIS and as required for environmental and operational permits.
Asset sale and salvage value assumptions include end of life re-sale values for mining and processing equipment; and recycle value for steel and pipe from the process plant and other facilities. (1) Net of asset sales. The Mt Todd FS contemplates an owner-operated mining fleet at initial capital of $86 million and sustaining capital of $565 million, inclusive of contingency.
Asset sale and salvage value assumptions include end of life re-sale values for mining and processing equipment; and recycle value for steel and pipe from the process plant and other facilities. (1) Net of asset sales. (2) Total capital per payable ounce of gold is a non-U.S. GAAP financial measure; see Item 7.
The present volume of water in the pit will not present any major issues when resuming operations in the Batman pit. 2023 Project Development Plans The Company is evaluating a smaller scale project at Mt Todd, targeting a significantly lower initial capital cost while maintaining operating costs very close to those estimated in the Mt Todd FS.
The Company expects to follow the drilling with studies of an initially smaller-scale project at Mt Todd, targeting a significantly lower initial capital cost and operating costs close to those estimated in the Mt Todd FS.